During the Project Assessment stage, we’re committed to evaluating potential project strategies. At this stage, we provide information about the proposed project plans on our website for stakeholders to review and provide feedback on, as well as holding in-person events within the local community demonstrating our collaborative approach to the project's development.
Stage 2: Early Development:
(Completed)
During Early Development, we concentrate on refining the project details, based on our initial assessment of key environmental, technical, and economic factors to identify the best performing approach. We would like to gain further input from communities through accessible in-person and in some cases online consultations, which are crucial in refining our plans and strategies before advancing to the application stage.
Stage 3: Project Refinement:
(Completed)
The Project Refinement stage is where we finalise project plans and submit the required planning applications to the relevant planning authorities. Communities and other key stakeholders can provide feedback directly to the appropriate body such as their local council and constituent representatives.
Stage 4: Construction Phase:
(Completed)
Within the construction phase we mobilise our workforce, contractors, and necessary equipment to begin construction. We maintain open channels of communication, allowing communities and stakeholders to submit feedback on the construction activities to our dedicated Community Liaison Managers, ensuring ongoing engagement to any thoughts or concerns while we carry out work in the area.
Stage 5: Operational Phase:
(Completed)
At this final stage, the project successfully moves into the operational phase, with the surrounding environment restored to its original state or better. Our Community Liaison Mangers continue to be available to address any questions or concerns, ensuring a lasting positive impact and strong community relations even after the construction activities conclude.
About the Project
The 132kV double circuit overhead line between Inverness and Keith Substations has a total route length of 92km, 29km between Inverness and Nairn and 63km between Nairn, Elgin and Keith. The section between Inverness and Beauly was reconductored and reinsulated in 1992. The section between Beauly and Keith was constructed in 1955 and forms an integral part of the transmission system, which was upgraded between 2018 and 2021.
We invested in the network to fully refurbish many of the towers and replace the existing wires (conductors) starting from Beauly Substation in 2018 and finishing at Keith Substation in 2021. The new wires are capable of carrying increased amounts of electricity whilst ensuring the security of electricity supply.
There are some very challenging aspects along the route, including major road crossings (A82, A862 ,A96 and the A9), numerous railway crossings, and water crossings at the River Ness and Caledonian Canal. The overhead line also crosses through the residential area of Holm as well as historic sites such as Culloden Battlefield.
Project Activities
Some of the project activities undertaken are as follows:
Some tree cutting along the route as required
A number of tower foundation upgrades as required
Tower steel strengthening
New access tracks into tower locations as required
Reconducting works (replacing existing conductors and fittings with new)
How we’re embracing artificial intelligence (AI) We intend to use AI to assist our experienced teams in the analysis of your feedback, so we can categorise key points raised more quickly. You can learn more about how we’re utilising AI on this dedicated web page.
We are committed to supporting the communities in the north of Scotland where we operate, both now and in the future. As part of our ongoing efforts to make a difference and have a positive impact on local communities, we are proud to offer volunteering days to local groups and charities, particularly in the areas that host our electricity infrastructure or where our proposed projects are located.
This month, we’re excited to announce the launch of our new Volunteering Webpage, designed to make it easier for local communities to request volunteering support from us. To request our help, simply complete the ‘Volunteering Nomination Form’ linked at the bottom of our new webpage. Please note, as our team works on a voluntary basis, it may take us some time to coordinate our people and match them with opportunities. We kindly ask for your patience as we work to keep up with volunteering demand.
Thank you for considering SSEN Transmission as a partner in your community efforts. Together, we can leave a positive, lasting legacy and help transform communities across the north of Scotland.
Project Completion
The Beauly-Inverness-Keith project team and our delivery partner Balfour Beatty celebrate a job well done as the final section of the Beauly to Keith overhead line upgrade project is completed, bringing to a close 3 years of hard work.
Hamilton Garden Housing Development
Essential works are being carried out in Elgin at the Hamilton Garden Housing Development. To view a short video from the project's Community Liaison Manager explaining the works, please click on the image.
SSEN Transmission teams have successfully completed the works between Beauly and Nairn
SSEN Transmission teams have successfully completed the works between Beauly and Nairn, which saw 40km of new overhead line installed over a 10-month period.Mike Cowie, SSEN Transmission’s Project Manager, said, “I’d like to thank the local communities for their patience as our teams have gone about their work, especially those who have been impacted by the various road closures and traffic management which have been in place along the route.“This phase of the project has been particularly challenging due to periods of bad weather we experienced, which meant that we had to re-schedule certain parts of the work plan, and so I’d like to thank everyone involved for their hard work and commitment which has seen the work completed on time. “
Temporary road closure
Temporary road closure starting on 9 July of a short section of Essich Road in the city during the hours of 09:00 -16:00 Monday to Friday. Works are expected to last approximately four weeks.
Balfour Beatty awarded Beauly to Keith overhead line and cabling works worth c. £43.5 million
Balfour Beatty, the international infrastructure group, has been awarded two contracts worth c. £43.5 million for the Beauly to Keith 132kV modernisation programme.Both contracts have been awarded by Scottish Hydro Electric Transmission plc, part of Scottish and Southern Electricity Networks (SSEN), through the existing F2 Overhead Line General Works Framework and the 132kV Underground Cable Works Framework.Read more at: https://www.balfourbeatty.com/news/balfour-beatty-awarded-beauly-to-keith-overhead-line-and-cabling-works-worth-c-435-million/
SSEN Transmission is responsible for maintaining and investing in the electricity transmission network in the north of Scotland and our network extends over a quarter of the UK’s land mass, crossing some of its most challenging terrain. Our operating area is home to vast renewable energy resources, and this is being harnessed by wind, hydro and marine generation. Working closely with National Grid Electricity System Operator (the 'ESO'), we enable electricity generators to connect to the transmission system, allowing the electricity generated by them to be transported to areas of demand across the country.
Following a minority stake sale which completed in November 2022, SSEN Transmission is now owned 75% by SSE plc and 25% by Ontario Teachers’ Pension Plan Board.
SSE plc sold its UK domestic electricity and gas retail business, along with domestic energy services to OVO Energy in January 2020 and no longer manages these customer accounts.
It’s the highest voltage electricity network in the UK – the ‘motorway network’ of the energy world. It transmits large quantities of electricity over long distances via wires carried on a system of mainly metal towers (pylons) and large substations. Transmission voltages in Scotland are 132kV, 275kV and 400kV. Larger generation schemes usually connect to the Transmission system.
The lower voltage parts of the system are called distribution networks. In Scotland, these local networks operate below 132kV whereas in England the distribution network includes 132kV.
As a stakeholder-led business, throughout the life of our projects, we aim to work positively with local communities and keep people informed about what we are doing. This is particularly important when we are developing new projects, we want to understand what local people think about our plans.
We always endeavour to take the time to discuss our proposals with local community councils and the wider affected community and to carry out engagement throughout each of the development stages, listening to feedback before finalising project plans. The feedback we receive is vital to help us develop proposals that reflect the views of a variety of stakeholder.
To find out more about a project, visit our project web pages which can be searched by location or area. Each project has a dedicated Community Liaison Manager that you can contact. You can find their contact details in the individual project pages, where you can also sign up to project updates.
Email:anthony.gill@sse.com Telephone: 07775 812900 Address: Prime Four Business Park, Kingswells Causeway, Aberdeen, AB15 8PU
Recite me
To support everyone online, we provide accessibility and language options on our website through ‘Recite me’. The accessibility and language support options provided by ‘Recite me’ include text-to-speech functionality, fully customisable styling features, reading aids, and a translation tool with over 100 languages, including 35 text-to-speech. Please select “Accessibility” on our website to try out our inclusive toolbar.
To make use of this function please click on the 3 'A's' button at the bottom left of the website.