Overview
Consent granted for Creag Dhubh-Dalmally overhead line
We welcome the decision made by Scottish Ministers to grant consent for the Creag Dhubh-Dalmally 275kV overhead line.
This project is part of a wider strategy to upgrade the capacity of the main electricity transmission network across Argyll and Kintyre from 132kV to 275kV, which is essential to enable the growth in renewable energy across the region.
The Argyll and Kintyre 275kV Strategy is also a key component of SSEN Transmission’s Pathway to 2030 programme, a £20bn investment that will support thousands of jobs and provide a major boost to local and national economies. These investments represent a major upgrade of the electricity transmission network across the north of Scotland to enable the connection and transportation of homegrown renewable energy to demand centres across the country, and are part of a GB-wide renewal of the transmission network that is required to meet UK and Scottish Government clean power and energy security targets.
The Section 37 planning application for the Creagh Dhubh-Dalmally 275kV overhead line was submitted to the Scottish Government in early summer 2022. In September 2022, Argyll and Bute Council’s Planning, Protective Services and Licensing Committee voted to raise an objection to the application, automatically triggering a Public Local Enquiry.
We now look forward to working with the local community and progressing the project in a timely manner, as we look to discharge planning conditions ahead of commencing construction.
About the Project
The existing transmission network in the Argyll region needs reinforcing to enable renewable generation to connect to the GB transmission network and to ensure security of electricity supply. The project elements inlcude:
- A new 13.3km 275kV overhead line between the proposed Creag Dhubh Substation and the tie in to the existing Scottish Power Energy Networks overhead line at Glen Lochy (Succoth Glen) (ECU Ref: ECU00002199)
- A tie in connection of the existing 132kV Taynuilt to Inveraray Overhead Line to the proposed new Creag Dhubh Substation (in development)
- A new 275/132kV substation adjacent to the existing Inveraray to Taynuilt 132kV Overhead Line (Creag Dhubh Substation) (Planning Ref: 22/00782/PP)
Find Out More About Argyll and Kintyre 275kV Strategy
Find Out More About Creag Dhubh Substation
3D Visualisation of the Project
In partnership with specialist company 3DW, we have created a video which allows stakeholders to visualise the Creag Dhubh – Dalmally Project. It has been created to increase transparency and understanding of the project.
Why is the Project Required?
The existing transmission network for Argyll was originally designed to serve a rural area with low demand for electricity. Requests from renewable generation developers to connect to the network in this area exceed the current capacity of the existing transmission network, meaning a new transmission circuit is required to meet demand from generation developers and ensure security of supply.
Stakeholder Engagement
We have been consulting locally on this project (formerly referred to as the North Argyll Project) since March 2016. The infographic shows our consultation process for this project.
The Creag Dhubh – Dalmally Project is part of a wider strategy to upgrade the main transmission network across Argyll to 275kV to support the growth in renewables across the region and the transition to Net Zero, supporting UK and Scottish Government climate change targets.
How we’re embracing artificial intelligence (AI)
We intend to use AI to assist our experienced teams in the analysis of your feedback, so we can categorise key points raised more quickly. You can learn more about how we’re utilising AI on this dedicated web page.
Project Updates
Project updates
Documents
Inveraray to Taynuilt (ITE/ITW) Tie-in Connection to Creag Dhubh Substation – Environmental Appraisal
-
Volume 3a Figure 5.15a Cumulative ZTV - Proposed Development & Creag Dhubh<29_B.pdf
- Type:
- Date:
- 23 October 2023
- Size:
- 12.2 MB
-
Volume 2 Technical Annex 1.1 EIA Screening Opinion Request Report Part 2_Optimized.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 5.5 MB
-
Volume 2 Technical Annex 1.1 EIA Screening Opinion Request Report Part 1.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 1.3 MB
-
Volume 3b Visualisations_Part1.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 5.8 MB
-
Volume 3b Visualisations_Part2.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 8.6 MB
-
Volume 3b Visualisations_Part3.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 8.9 MB
-
Volume 3b Visualisations_Part4.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 8.6 MB
-
Volume 3b Visualisations_Part5.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 7.2 MB
-
Volume 3b Visualisations_Part6.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 7.5 MB
-
Volume 3b Visualisations_Part7.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 2.6 MB
-
Volume 3a Figure 1.1 Site Location.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 4.8 MB
-
Volume 3a Figure 1.2 Associated Developments.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 2.9 MB
-
Volume 3a Figure 2.1 Surrounding Environmental Constraints.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 11.2 MB
-
Volume 3a Figure 2.2 Cumulative Developments.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 8.5 MB
-
Volume 3a Figure 3.1a Proposed Development.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 1.1 MB
-
Volume 3a Figure 3.1b Proposed Development and Associated Works.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 1.6 MB
-
Volume 3a Figure 3.2 Landtake .pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 1.2 MB
-
Volume 3a Figure 4.1 Ecology and Ornithology Constraints.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 3.8 MB
-
Volume 3a Figure 4.2 Phase 1 Habitats.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 1.3 MB
-
Volume 3a Figure 4.3 NVC.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 1.2 MB
-
Volume 3a Figure 4.4 GWDTE.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 1.4 MB
-
Volume 3a Figure 5.1 Site Location and LVIA 10 km Study Area.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 7.9 MB
-
Volume 3a Figure 5.15 Cumulative Developments and Viewpoint Locations.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 9 MB
-
Volume 3a Figure 5.15b Cumulative ZTV - Proposed Development & LT194 & LT40.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 12.3 MB
-
Volume 3a Figure 5.2a ZTV Existing Towers.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 7 MB
-
Volume 3a Figure 5.2b ZTV Proposed Development Temporary Poles.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 7.1 MB
-
Volume 3a Figure 5.2c ZTV Proposed Development Towers.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 7 MB
-
Volume 3a Figure 5.3 Topography and LVA Study Area.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 11.9 MB
-
Volume 3a Figure 5.4 Landscape Character Types within LVA Study Area.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 11.4 MB
-
Volume 3a Figure 5.5 Landscape Designations and Classifications.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 11.5 MB
-
Volume 3a Figure 5.6 Viewpoint Locations and Visual Receptors.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 12.1 MB
-
Volume 3a Figure 6.1 Cultural Heritage Inner Study Area .pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 2 MB
-
Volume 3a Figure 6.2 Outer Study Area ZTV.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 4.9 MB
-
Volume 3a Figure 6.3 Outer Study Area ZTV +20%.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 4.8 MB
-
Volume 3aFigure 5.15c Cumulative ZTV - Proposed Development & Ladyfield Wind Farm.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 12.2 MB
-
EA_ Volume 1_Contents.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 87.2 KB
-
EA_Cover Pages.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 1.3 MB
-
EA_Glossary and Abbreviations.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 155 KB
-
EA_Volume 2 Contents.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 48.6 KB
-
EA_Volume 3a Contents.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 47.4 KB
-
EA_Volume 3b Contents.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 45.9 KB
-
Volume 1 Chapter 4 Ecology and Ornithology .pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 312.1 KB
-
Volume 1 Chapter 5 Landscape and Visual.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 558.2 KB
-
Volume 1 Chapter 6 Cultural Heritage .pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 331.1 KB
-
Volume 1 Chapter 7 Hydrology and Geology.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 692.7 KB
-
Volume 1 Chapter 8 Schedule of Mitigation.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 276.3 KB
-
Volume 1 Chapters 1-3 Front Chapters.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 558 KB
-
Volume 2 Technical Annex 2.1 Woodland Report combined_Optimized.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 5.1 MB
-
Volume 2 Technical Annex 2.2 Traffic Calculations.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 79.2 KB
-
Volume 2 Technical Annex 3.2 Outline CEMP.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 5.9 MB
-
Volume 2 Technical Annex 4.1 Ecology and Ornithology Methodology and Results.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 307.9 KB
-
Volume 2 Technical Annex 5.1 Landscape and Visual .pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 358.5 KB
-
Volume 2 Technical Annex 6.1 Cultural Heritage Inner Study Area.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 174.8 KB
-
Volume 2 Technical Annex 6.2 Cultural Heritage Outer Study Area.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 200.2 KB
-
Volume 2 Technical Annex 7.1 Peat Survey Results_Combined_Optimized.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 2.3 MB
-
Volume 2 Technical Annex 7.2 Outline PMP.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 198 KB
-
Volume 2 Technical Annex 7.3 PLHRA_Combined_Optimized.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 4.4 MB
Overhead Line Section 37 advert
-
S37 Advert
- Type:
- Date:
- 05 July 2022
- Size:
- 116.2 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
Overhead Line Section 37 covering letter
-
Cover Letter
- Type:
- Date:
- 24 May 2022
- Size:
- 203.3 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
Overhead Line Section 37 Planning statement
-
Planning Statement
- Type:
- Date:
- 24 May 2022
- Size:
- 794.6 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
Overhead Line Section 37 Supporting documents
-
Bellmouth Access Example
- Type:
- Date:
- 24 May 2022
- Size:
- 898.5 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Bellmouth Construction Detail Example
- Type:
- Date:
- 24 May 2022
- Size:
- 248.7 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Bellmouth General Arrangement_Example
- Type:
- Date:
- 24 May 2022
- Size:
- 1 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
EIA Glossary and Contents
- Type:
- Date:
- 24 May 2022
- Size:
- 668.6 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
PAC_Report on Consultation_Nov 2020
- Type:
- Date:
- 24 May 2022
- Size:
- 4.6 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
PAC_Report on Consultation_Nov 2021
- Type:
- Date:
- 24 May 2022
- Size:
- 11.4 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Schedule of Environmental Mitigation
- Type:
- Date:
- 24 May 2022
- Size:
- 11.4 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
Overhead Line Section 37 volume 1 non technical summary
-
Volume 1 Non Technical Summary
- Type:
- Date:
- 23 May 2022
- Size:
- 2.4 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
Overhead Line Section 37 volume 2 main report
-
Volume 2 - Chapter 1
- Type:
- Date:
- 23 May 2022
- Size:
- 594.3 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 2 - Chapter 10
- Type:
- Date:
- 23 May 2022
- Size:
- 509 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 2 - Chapter 11
- Type:
- Date:
- 23 May 2022
- Size:
- 345.9 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 2 - Chapter 12
- Type:
- Date:
- 23 May 2022
- Size:
- 657.5 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 2 - Chapter 13
- Type:
- Date:
- 23 May 2022
- Size:
- 466.1 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 2 - Chapter 14
- Type:
- Date:
- 23 May 2022
- Size:
- 293.7 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 2 - Chapter 15
- Type:
- Date:
- 23 May 2022
- Size:
- 293.7 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 2 - Chapter 2
- Type:
- Date:
- 23 May 2022
- Size:
- 1.6 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 2 - Chapter 3
- Type:
- Date:
- 23 May 2022
- Size:
- 2.5 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 2 - Chapter 4
- Type:
- Date:
- 23 May 2022
- Size:
- 378.4 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 2 - Chapter 5
- Type:
- Date:
- 23 May 2022
- Size:
- 269.4 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 2 - Chapter 6
- Type:
- Date:
- 23 May 2022
- Size:
- 620.2 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 2 - Chapter 7
- Type:
- Date:
- 23 May 2022
- Size:
- 525.5 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 2 - Chapter 8
- Type:
- Date:
- 23 May 2022
- Size:
- 603.8 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 2 - Chapter 9
- Type:
- Date:
- 23 May 2022
- Size:
- 600 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
Overhead Line Section 37 volume 3A figures
-
Volume 3a - Figure 10.2
- Type:
- Date:
- 31 August 2022
- Size:
- 9 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 3.3
- Type:
- Date:
- 31 August 2022
- Size:
- 4.5 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 1.1
- Type:
- Date:
- 23 May 2022
- Size:
- 2.7 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 10.1
- Type:
- Date:
- 23 May 2022
- Size:
- 6 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 10.3
- Type:
- Date:
- 23 May 2022
- Size:
- 10 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 10.4
- Type:
- Date:
- 23 May 2022
- Size:
- 4.4 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 10.5
- Type:
- Date:
- 23 May 2022
- Size:
- 3.4 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 10.6
- Type:
- Date:
- 23 May 2022
- Size:
- 3.3 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 10.7
- Type:
- Date:
- 23 May 2022
- Size:
- 6.7 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 10.8
- Type:
- Date:
- 23 May 2022
- Size:
- 3.6 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 11.4
- Type:
- Date:
- 23 May 2022
- Size:
- 2.2 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 11.5
- Type:
- Date:
- 23 May 2022
- Size:
- 4 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 11.6
- Type:
- Date:
- 23 May 2022
- Size:
- 5.9 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 12.1
- Type:
- Date:
- 23 May 2022
- Size:
- 6 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 12.2
- Type:
- Date:
- 23 May 2022
- Size:
- 6 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 13.1
- Type:
- Date:
- 23 May 2022
- Size:
- 8.7 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 14.1
- Type:
- Date:
- 23 May 2022
- Size:
- 8.5 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 2.1 a-j
- Type:
- Date:
- 23 May 2022
- Size:
- 8.8 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 3.1
- Type:
- Date:
- 23 May 2022
- Size:
- 4.4 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 3.2
- Type:
- Date:
- 23 May 2022
- Size:
- 3.7 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 6.1
- Type:
- Date:
- 23 May 2022
- Size:
- 9.2 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 6.2
- Type:
- Date:
- 23 May 2022
- Size:
- 11.6 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 6.3
- Type:
- Date:
- 23 May 2022
- Size:
- 9 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 6.4
- Type:
- Date:
- 23 May 2022
- Size:
- 8.7 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 6.6
- Type:
- Date:
- 23 May 2022
- Size:
- 9.1 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 7.1
- Type:
- Date:
- 23 May 2022
- Size:
- 8.5 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 7.2
- Type:
- Date:
- 23 May 2022
- Size:
- 5.6 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 7.3
- Type:
- Date:
- 23 May 2022
- Size:
- 5.7 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 7.4
- Type:
- Date:
- 23 May 2022
- Size:
- 5.7 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 8.1a
- Type:
- Date:
- 23 May 2022
- Size:
- 6 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 8.1b
- Type:
- Date:
- 23 May 2022
- Size:
- 6 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 8.2
- Type:
- Date:
- 23 May 2022
- Size:
- 4.6 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 8.3a
- Type:
- Date:
- 23 May 2022
- Size:
- 5.2 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 8.3b
- Type:
- Date:
- 23 May 2022
- Size:
- 6.2 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 8.3c
- Type:
- Date:
- 23 May 2022
- Size:
- 6.2 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 8.4a
- Type:
- Date:
- 23 May 2022
- Size:
- 5.1 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 8.4b
- Type:
- Date:
- 23 May 2022
- Size:
- 6.1 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 8.4c
- Type:
- Date:
- 23 May 2022
- Size:
- 6.2 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 8.5a
- Type:
- Date:
- 23 May 2022
- Size:
- 6.1 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 8.5b
- Type:
- Date:
- 23 May 2022
- Size:
- 6.1 MB
-
Volume 3a - Figure 8.7
- Type:
- Date:
- 23 May 2022
- Size:
- 5.7 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 9.1
- Type:
- Date:
- 23 May 2022
- Size:
- 8.1 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 9.2
- Type:
- Date:
- 23 May 2022
- Size:
- 3 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3a - Figure 9.3
- Type:
- Date:
- 23 May 2022
- Size:
- 3 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
Overhead Line Section 37 volume 3B visualisations
-
Volume 3b Figure 8.8a
- Type:
- Date:
- 24 May 2022
- Size:
- 2.5 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3b Figure 8.8b
- Type:
- Date:
- 24 May 2022
- Size:
- 1.8 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3b Figure 8.8c
- Type:
- Date:
- 24 May 2022
- Size:
- 1.8 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3b Figure 8.8d
- Type:
- Date:
- 24 May 2022
- Size:
- 1.8 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3b Figure 8.8e
- Type:
- Date:
- 24 May 2022
- Size:
- 2.3 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3b Figure 8.8f
- Type:
- Date:
- 24 May 2022
- Size:
- 1.9 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3b Figure 8.8g
- Type:
- Date:
- 24 May 2022
- Size:
- 2.1 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3b Figure 8.8h
- Type:
- Date:
- 24 May 2022
- Size:
- 3.2 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3b Figure 8.8i
- Type:
- Date:
- 24 May 2022
- Size:
- 2.1 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3b Figure 8.8j
- Type:
- Date:
- 24 May 2022
- Size:
- 2.1 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3b Figure 8.8k
- Type:
- Date:
- 24 May 2022
- Size:
- 3.2 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3b Figure 8.8l
- Type:
- Date:
- 24 May 2022
- Size:
- 1.8 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3b Figure 8.8m
- Type:
- Date:
- 24 May 2022
- Size:
- 2.1 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3b Figure 8.8n
- Type:
- Date:
- 24 May 2022
- Size:
- 1.7 MB
-
Volume 3b Figure 8.8o
- Type:
- Date:
- 24 May 2022
- Size:
- 1.8 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3b Figure 8.8p
- Type:
- Date:
- 24 May 2022
- Size:
- 1.9 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3b Figure 8.8q
- Type:
- Date:
- 24 May 2022
- Size:
- 4.4 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3b Figure 8.8r
- Type:
- Date:
- 24 May 2022
- Size:
- 2.2 MB
-
Volume 3b Figure 8.8s
- Type:
- Date:
- 24 May 2022
- Size:
- 2.5 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3b Figures 8.8.2b-8.8.6c
- Type:
- Date:
- 24 May 2022
- Size:
- 4.5 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3b Figures 9.10_9.16
- Type:
- Date:
- 24 May 2022
- Size:
- 6.2 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 3b Figures 9.4_9.9
- Type:
- Date:
- 24 May 2022
- Size:
- 4.9 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
Overhead Line Section 37 volume 4 technical appendices
-
LT29-M21 Fig 11.7Kep Landscape
- Type:
- Date:
- 24 May 2022
- Size:
- 5 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
LT29-M22 Fig 11.8 Kepp Current
- Type:
- Date:
- 24 May 2022
- Size:
- 4.6 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
LT29-M23 Fig11.9 Kepp LTFP Fell
- Type:
- Date:
- 24 May 2022
- Size:
- 5 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
LT29-M2411.10 Kepp LTFP Restock
- Type:
- Date:
- 24 May 2022
- Size:
- 4.6 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
LT29-M25 Fig 11.11 Kepp Felling
- Type:
- Date:
- 24 May 2022
- Size:
- 4.9 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
LT29-M26 Fig 11.12 Kepp Restock Queries
- Type:
- Date:
- 24 May 2022
- Size:
- 3.6 MB
-
R170_3673_Fig10.8.1_SuperficialGeology_A
- Type:
- Date:
- 24 May 2022
- Size:
- 4.8 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
R170_3673_Fig10.8.2_SolidGeology_A
- Type:
- Date:
- 24 May 2022
- Size:
- 6.7 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
R170_3673_Fig10.8.3_Hydrogeology_A
- Type:
- Date:
- 24 May 2022
- Size:
- 6.4 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
R170_3673_Fig10.8.4_SurfaceWaterAcc_B
- Type:
- Date:
- 24 May 2022
- Size:
- 4.1 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
R170_3673_Fig10.8.5_GWDTE_E
- Type:
- Date:
- 24 May 2022
- Size:
- 15.8 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
R170_3673_Fig10.8.6_GWDTE_Hydro_A
- Type:
- Date:
- 24 May 2022
- Size:
- 15.1 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 10.1
- Type:
- Date:
- 24 May 2022
- Size:
- 3.2 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 10.2
- Type:
- Date:
- 24 May 2022
- Size:
- 7.9 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 10.3 Part 1
- Type:
- Date:
- 24 May 2022
- Size:
- 831 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 10.3 Part 2a
- Type:
- Date:
- 24 May 2022
- Size:
- 9.7 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 10.3 Part 2b
- Type:
- Date:
- 24 May 2022
- Size:
- 5.9 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 10.3 Part 2c
- Type:
- Date:
- 24 May 2022
- Size:
- 5.7 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 10.3 Part 2d
- Type:
- Date:
- 24 May 2022
- Size:
- 6.8 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 10.4 Part 1
- Type:
- Date:
- 24 May 2022
- Size:
- 5.6 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 10.4 Part 2a
- Type:
- Date:
- 24 May 2022
- Size:
- 5.7 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 10.4 Part 2b
- Type:
- Date:
- 24 May 2022
- Size:
- 5.8 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 10.5
- Type:
- Date:
- 24 May 2022
- Size:
- 513.1 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 10.6
- Type:
- Date:
- 24 May 2022
- Size:
- 14.3 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 10.7
- Type:
- Date:
- 24 May 2022
- Size:
- 265.6 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 10.8
- Type:
- Date:
- 24 May 2022
- Size:
- 657.8 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 11.1b_Optimized
- Type:
- Date:
- 24 May 2022
- Size:
- 6.1 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 11.1c
- Type:
- Date:
- 24 May 2022
- Size:
- 2.6 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 11.1d_Optimized
- Type:
- Date:
- 24 May 2022
- Size:
- 5.1 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 11.1e
- Type:
- Date:
- 24 May 2022
- Size:
- 6.4 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 11.1f
- Type:
- Date:
- 24 May 2022
- Size:
- 4 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 11.1g
- Type:
- Date:
- 24 May 2022
- Size:
- 1.8 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 11.1h
- Type:
- Date:
- 24 May 2022
- Size:
- 3 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 11.1i
- Type:
- Date:
- 24 May 2022
- Size:
- 655.7 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 11.2
- Type:
- Date:
- 24 May 2022
- Size:
- 304.8 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 11.3
- Type:
- Date:
- 24 May 2022
- Size:
- 303.7 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 12.1
- Type:
- Date:
- 24 May 2022
- Size:
- 223.3 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 12.2
- Type:
- Date:
- 24 May 2022
- Size:
- 169.2 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 2.1
- Type:
- Date:
- 24 May 2022
- Size:
- 58 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 2.2
- Type:
- Date:
- 24 May 2022
- Size:
- 1011.4 KB
-
Volume 4 - Technical Appendix 2.3
- Type:
- Date:
- 24 May 2022
- Size:
- 4.1 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 2.4
- Type:
- Date:
- 24 May 2022
- Size:
- 3.7 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 3.1
- Type:
- Date:
- 24 May 2022
- Size:
- 11.4 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 4.1
- Type:
- Date:
- 24 May 2022
- Size:
- 1.6 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 4.2
- Type:
- Date:
- 24 May 2022
- Size:
- 8 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 4.3
- Type:
- Date:
- 24 May 2022
- Size:
- 490 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 6.1
- Type:
- Date:
- 24 May 2022
- Size:
- 588.2 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 6.3
- Type:
- Date:
- 24 May 2022
- Size:
- 559.8 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 7.1
- Type:
- Date:
- 24 May 2022
- Size:
- 478.4 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 8.1
- Type:
- Date:
- 24 May 2022
- Size:
- 248.3 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 8.2
- Type:
- Date:
- 24 May 2022
- Size:
- 350.6 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 8.3
- Type:
- Date:
- 24 May 2022
- Size:
- 382.8 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 8.4
- Type:
- Date:
- 24 May 2022
- Size:
- 323.1 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 8.5
- Type:
- Date:
- 24 May 2022
- Size:
- 338.7 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 8.6
- Type:
- Date:
- 24 May 2022
- Size:
- 465.2 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 8.7
- Type:
- Date:
- 24 May 2022
- Size:
- 408 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 8.8
- Type:
- Date:
- 24 May 2022
- Size:
- 3 MB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 9.1
- Type:
- Date:
- 24 May 2022
- Size:
- 446.3 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 9.2
- Type:
- Date:
- 24 May 2022
- Size:
- 443.8 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 9.3
- Type:
- Date:
- 24 May 2022
- Size:
- 287.8 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
-
Volume 4 - Technical Appendix 11.1a
- Type:
- Date:
- 24 May 2022
- Size:
- 774.2 KB
Related Projects: Creag Dhubh - Dalmally 275kV Connection
Project documents
-
Argyll and Kintyre 275kV Strategy Consultation Booklet- July 2021
- Type:
- Date:
- 16 September 2022
- Size:
- 10.2 MB
-
Argyll and Kintyre 275kV Strategy Consultation Poster July 2021
- Type:
- Date:
- 16 September 2022
- Size:
- 100.7 KB
-
Argyll Generation Seminar - Slide Pack - April 2021
- Type:
- Date:
- 16 September 2022
- Size:
- 1.7 MB
-
Argyll Regional Webinar Presentation - March 2021
- Type:
- Date:
- 16 September 2022
- Size:
- 3.5 MB
-
Creag Dhubh - Dalmally 275kV - Alignment Selection Consultation Document - March 2018
- Type:
- Date:
- 16 September 2022
- Size:
- 4.2 MB
-
Creag Dhubh - Dalmally 275kV - Consultation Booklet - March 2018
- Type:
- Date:
- 16 September 2022
- Size:
- 1.1 MB
-
Creag Dhubh - Dalmally 275kV - Consultation Booklet - October 2016
- Type:
- Date:
- 16 September 2022
- Size:
- 1.9 MB
-
Creag Dhubh - Dalmally 275kV - Consultation Booklet - September 2020
- Type:
- Date:
- 16 September 2022
- Size:
- 4.9 MB
-
Creag Dhubh - Dalmally 275kV - Consultation Document - August 2020
- Type:
- Date:
- 16 September 2022
- Size:
- 3.3 MB
-
Creag Dhubh - Dalmally 275kV - Consultation Document - June 2021
- Type:
- Date:
- 16 September 2022
- Size:
- 2.4 MB
-
Creag Dhubh - Dalmally 275kV - Consultation Options Map -2020
- Type:
- Date:
- 16 September 2022
- Size:
- 515.3 KB
-
Creag Dhubh - Dalmally 275kV - EIA Scoping Report - December 2020
- Type:
- Date:
- 16 September 2022
- Size:
- 1.6 MB
-
Creag Dhubh - Dalmally 275kV - Information Boards - March 2016
- Type:
- Date:
- 16 September 2022
- Size:
- 3.2 MB
-
Creag Dhubh - Dalmally 275kV - Virtual Consultation Poster - Summer 2020
- Type:
- Date:
- 16 September 2022
- Size:
- 562.6 KB
-
Creag Dhubh - Dalmally 275kV - Virtual Information Boards - Summer 2020
- Type:
- Date:
- 16 September 2022
- Size:
- 4.8 MB
-
Creag Dhubh - Dalmally 275kV- Report on Consultation - November 2020
- Type:
- Date:
- 16 September 2022
- Size:
- 4.6 MB
-
Creag Dhubh - Dalmally 275kV Report on Consultation - November 2021
- Type:
- Date:
- 16 September 2022
- Size:
- 11.4 MB
-
Creag Dhubh Substation - Pre-Application Consultation Report - November 2021
- Type:
- Date:
- 16 September 2022
- Size:
- 5.4 MB
-
Creag Dhubh Substation- Options Appraisal - August 2015
- Type:
- Date:
- 16 September 2022
- Size:
- 28 MB
-
Dalmally Community Centre Meeting - Slides - October-2021
- Type:
- Date:
- 16 September 2022
- Size:
- 17.1 MB
-
Dalmally Community FAQ - October 2021
- Type:
- Date:
- 16 September 2022
- Size:
- 460.7 KB
-
Dalmally Community Update Letter - May 2022
- Type:
- Date:
- 16 September 2022
- Size:
- 204.8 KB
-
Glenorchy and Innishail Community Council - Underground Cabling Update Presentation - January 2018
- Type:
- Date:
- 16 September 2022
- Size:
- 9.5 MB
-
Summer 2020 Consultation - Option 1 Map
- Type:
- Date:
- 16 September 2022
- Size:
- 4.8 MB
-
Summer 2020 Consultation - Option 2 Map
- Type:
- Date:
- 16 September 2022
- Size:
- 3.6 MB
-
Summer 2020 Consultation - Option 3 Map
- Type:
- Date:
- 16 September 2022
- Size:
- 3.5 MB
-
Virtual Consultation User Guide
- Type:
- Date:
- 16 September 2022
- Size:
- 774.8 KB
FAQs
FAQs
Recite me
To make use of this function please click on the 3 'A's' button at the bottom left of the website.