Overview
About the Project
This project consists of the construction of a new 275/132kV Gas Insulated Switchgear Substation at Creag Dhubh, with this connected from Creag Dhubh to the Scottish Power Transmission Dalmally – Windyhill 275kV Overhead Line via 13.5km of proprosed new 275kV double circuit steel tower Overhead Line.
Why is the Project Required?
The existing transmission network for Argyll was originally designed to serve a rural area with low demand for electricity. Requests from renewable generation developers to connect to the network in this area exceed the current capacity of the existing transmission network, meaning a new transmission circuit is required to meet demand from generation developers and ensure security of supply.
Community Engagement
Throughout the life of our projects, we aim to work positively with local communities and keep people informed about what we are doing. This is particularly important when we are developing a proposal and we want to understand what local people think about our plans.
We endeavour to take the time to discuss proposals with local community councils, encourage engagement from the wider community and listen to the feedback we receive.
We will do our best to answer any questions and address issues or concerns that are raised with us.
When our project progresses into construction, we will continue working closely with the local community to ensure that our work has as little impact on the lives of those living and working in the area and as many long term positive effects as possible.
How we’re embracing artificial intelligence (AI)
We intend to use AI to assist our experienced teams in the analysis of your feedback, so we can categorise key points raised more quickly. You can learn more about how we’re utilising AI on this dedicated web page.
Project Updates
Project updates
Project Documents
Inveraray to Taynuilt (ITE/ITW) Tie-in Connection to Creag Dhubh Substation – Environmental Appraisal
-
Volume 3a Figure 5.15a Cumulative ZTV - Proposed Development & Creag Dhubh<29_B.pdf
- Type:
- Date:
- 23 October 2023
- Size:
- 12.2 MB
-
Volume 2 Technical Annex 1.1 EIA Screening Opinion Request Report Part 2_Optimized.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 5.5 MB
-
Volume 2 Technical Annex 1.1 EIA Screening Opinion Request Report Part 1.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 1.3 MB
-
Volume 3b Visualisations_Part1.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 5.8 MB
-
Volume 3b Visualisations_Part2.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 8.6 MB
-
Volume 3b Visualisations_Part3.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 8.9 MB
-
Volume 3b Visualisations_Part4.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 8.6 MB
-
Volume 3b Visualisations_Part5.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 7.2 MB
-
Volume 3b Visualisations_Part6.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 7.5 MB
-
Volume 3b Visualisations_Part7.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 2.6 MB
-
Volume 3a Figure 1.1 Site Location.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 4.8 MB
-
Volume 3a Figure 1.2 Associated Developments.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 2.9 MB
-
Volume 3a Figure 2.1 Surrounding Environmental Constraints.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 11.2 MB
-
Volume 3a Figure 2.2 Cumulative Developments.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 8.5 MB
-
Volume 3a Figure 3.1a Proposed Development.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 1.1 MB
-
Volume 3a Figure 3.1b Proposed Development and Associated Works.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 1.6 MB
-
Volume 3a Figure 3.2 Landtake .pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 1.2 MB
-
Volume 3a Figure 4.1 Ecology and Ornithology Constraints.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 3.8 MB
-
Volume 3a Figure 4.2 Phase 1 Habitats.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 1.3 MB
-
Volume 3a Figure 4.3 NVC.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 1.2 MB
-
Volume 3a Figure 4.4 GWDTE.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 1.4 MB
-
Volume 3a Figure 5.1 Site Location and LVIA 10 km Study Area.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 7.9 MB
-
Volume 3a Figure 5.15 Cumulative Developments and Viewpoint Locations.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 9 MB
-
Volume 3a Figure 5.15b Cumulative ZTV - Proposed Development & LT194 & LT40.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 12.3 MB
-
Volume 3a Figure 5.2a ZTV Existing Towers.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 7 MB
-
Volume 3a Figure 5.2b ZTV Proposed Development Temporary Poles.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 7.1 MB
-
Volume 3a Figure 5.2c ZTV Proposed Development Towers.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 7 MB
-
Volume 3a Figure 5.3 Topography and LVA Study Area.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 11.9 MB
-
Volume 3a Figure 5.4 Landscape Character Types within LVA Study Area.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 11.4 MB
-
Volume 3a Figure 5.5 Landscape Designations and Classifications.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 11.5 MB
-
Volume 3a Figure 5.6 Viewpoint Locations and Visual Receptors.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 12.1 MB
-
Volume 3a Figure 6.1 Cultural Heritage Inner Study Area .pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 2 MB
-
Volume 3a Figure 6.2 Outer Study Area ZTV.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 4.9 MB
-
Volume 3a Figure 6.3 Outer Study Area ZTV +20%.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 4.8 MB
-
Volume 3aFigure 5.15c Cumulative ZTV - Proposed Development & Ladyfield Wind Farm.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 12.2 MB
-
EA_ Volume 1_Contents.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 87.2 KB
-
EA_Cover Pages.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 1.3 MB
-
EA_Glossary and Abbreviations.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 155 KB
-
EA_Volume 2 Contents.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 48.6 KB
-
EA_Volume 3a Contents.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 47.4 KB
-
EA_Volume 3b Contents.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 45.9 KB
-
Volume 1 Chapter 4 Ecology and Ornithology .pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 312.1 KB
-
Volume 1 Chapter 5 Landscape and Visual.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 558.2 KB
-
Volume 1 Chapter 6 Cultural Heritage .pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 331.1 KB
-
Volume 1 Chapter 7 Hydrology and Geology.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 692.7 KB
-
Volume 1 Chapter 8 Schedule of Mitigation.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 276.3 KB
-
Volume 1 Chapters 1-3 Front Chapters.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 558 KB
-
Volume 2 Technical Annex 2.1 Woodland Report combined_Optimized.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 5.1 MB
-
Volume 2 Technical Annex 2.2 Traffic Calculations.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 79.2 KB
-
Volume 2 Technical Annex 3.2 Outline CEMP.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 5.9 MB
-
Volume 2 Technical Annex 4.1 Ecology and Ornithology Methodology and Results.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 307.9 KB
-
Volume 2 Technical Annex 5.1 Landscape and Visual .pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 358.5 KB
-
Volume 2 Technical Annex 6.1 Cultural Heritage Inner Study Area.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 174.8 KB
-
Volume 2 Technical Annex 6.2 Cultural Heritage Outer Study Area.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 200.2 KB
-
Volume 2 Technical Annex 7.1 Peat Survey Results_Combined_Optimized.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 2.3 MB
-
Volume 2 Technical Annex 7.2 Outline PMP.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 198 KB
-
Volume 2 Technical Annex 7.3 PLHRA_Combined_Optimized.pdf
- Type:
- Date:
- 17 March 2023
- Size:
- 4.4 MB
Project FAQs
FAQs
Register for Project Updates
Your subscription preferences
We would like to send you relevant communications via email, such as invitations to stakeholder events, surveys, updates on projects and future developments. If you are happy to receive email updates, please opt-in by ticking the box on our registration form. You can unsubscribe at any time by contacting us at stakeholder.admin@sse.com, or by clicking the 'unsubscribe' link which appears at the end of our emails.
GDPR
When contacting us, please only submit relevant information. Please do not include sensitive personal data or bank details.
Privacy Notice
For information on how we collect and process your data, please see our Privacy Notice. If you do not have access to the website or would like a hard copy, please contact us.
Recite me
To make use of this function please click on the 3 'A's' button at the bottom left of the website.