Overview
About the Project
The East Coast 275kV Upgrade is the first part of the phased onshore reinforcement of the electricity transmission network on the east coast of Scotland. These reinforcements comprise works on existing infrastructure in both ours and Scottish Power Energy Networks (SPEN) area, with the bulk of the works in our area.
The main advantage of a two-stage approach is this allows for earlier delivery of increased capacity on the network in this region. This will also help resolve the issue of overloading and congestion on the transmission network.
The east coast steel lattice towers and the overhead lines which they support are currently operating at 275kV. The projected growth in generation capacity within our area gives rise to increased north to south power transfer requirements and therefore the overhead lines are required to transfer more power. As a result, the conductors will operate at an elevated temperature, which can cause the conductors to sag. As a responsible operator we have modelled the future sag and under this project will undertake works to ensure the conductors remain within a safe clearance height.
The works required are termed as re-profiling works, where works such as vegetation clearance or changing of fittings on some towers to raise the conductor will be undertaken. This will ensure safe clearance between the ground and the conductor is maintained.
Why is the Project Required?
As part of our statutory and transmission licence obligations, we have a number of duties including:
- the development and maintenance of an efficient, coordinated and economical system of electricity transmission
- to facilitate competition in the supply and generation of electricity
- to ensure that the security of the network is maintained as the demand and/or generation connections change over time
We have a licence obligation to invest in our existing assets to maintain network health and condition. We also have a statutory duty under the Electricity Safety, Quality and Continuity Regulations 2002 to ensure that the electricity transmission network is fit for purpose.
The National Electricity Transmission System Security and Quality of Supply Standard (NETS SQSS) provides the deterministic criteria that we must use to plan and design the transmission system. The criteria require that there are neither equipment overloads nor voltage violations under intact conditions. The criteria also require that there is no unacceptable overloading of any primary transmission equipment or unacceptable voltage conditions under planned or unplanned outage conditions.
Community Engagement
Throughout the life of our projects, we aim to work positively with local communities and keep people informed about what we are doing. This is particularly important when we are developing a proposal and we want to understand what local people think about our plans.
We endeavour to take the time to discuss proposals with local community councils, encourage engagement from the wider community and listen to the feedback we receive.
We will do our best to answer any questions and address issues or concerns that are raised with us.
When our project progresses into construction, we will continue working closely with the local community to ensure that our work has as little impact on the lives of those living and working in the area and as many long term positive effects as possible.
How we’re embracing artificial intelligence (AI)
We intend to use AI to assist our experienced teams in the analysis of your feedback, so we can categorise key points raised more quickly. You can learn more about how we’re utilising AI on this dedicated web page.
Project Updates
Project updates
Documents
-
East Coast 275kV and 400kV Overhead Line Reinforcement Projects Information Booklet - April 2021
- Type:
- Date:
- 06 April 2021
- Size:
- 3.4 MB
-
North East 400kV and Eastern Reinforcements Information Booklet - November 2019
- Type:
- Date:
- 20 November 2019
- Size:
- 4.5 MB
Gallery
Progress Gallery
A selection of photographs taken on site documenting the project construction progress of phase 1 which consists of overhead line works associated with the new Alyth substation that is currently in construction.
FAQs
FAQs
Recite me
To make use of this function please click on the 3 'A's' button at the bottom left of the website.
