Overview
About the Project
- The existing Grid Supply Point (GSP) substation at Cassley is at capacity
- The existing overhead lines between Lairg GSP and Cassley GSP are also at capacity
Find Out More About Lairg - Loch Buidhe Projects
Why is the Project Required?
As the transmission licence holder in the north of Scotland we have a duty under Section 9 of the Electricity Act 1989 to facilitate competition in the generation and supply of electricity. We have obligations to offer non-discriminatory terms for connection to the transmission system, both for new generation and for new sources of electricity demand.
The aim of the project is to enable renewable energy to connect to our transmission network. Under our Network Operators Licence this connection should be efficient, co-ordinated and economic, whilst having the least possible impact on the environment.
Community Engagement
Throughout the life of our projects, we aim to work positively with local communities and keep people informed about what we are doing. This is particularly important when we are developing a proposal and we want to understand what local people think about our plans.
We endeavour to take the time to discuss proposals with local community councils, encourage engagement from the wider community and listen to the feedback we receive.
We will do our best to answer any questions and address issues or concerns that are raised with us.
When our project progresses into construction, we will continue working closely with the local community to ensure that our work has as little impact on the lives of those living and working in the area and as many long term positive effects as possible.
How we’re embracing artificial intelligence (AI)
We intend to use AI to assist our experienced teams in the analysis of your feedback, so we can categorise key points raised more quickly. You can learn more about how we’re utilising AI on this dedicated web page.
Project Updates
Project updates
Project FAQs
FAQs
Register for Project Updates
Your subscription preferences
We would like to send you relevant communications via email, such as invitations to stakeholder events, surveys, updates on projects and future developments. If you are happy to receive email updates, please opt-in by ticking the box on our registration form. You can unsubscribe at any time by contacting us at stakeholder.admin@sse.com, or by clicking the 'unsubscribe' link which appears at the end of our emails.
GDPR
When contacting us, please only submit relevant information. Please do not include sensitive personal data or bank details.
Privacy Notice
For information on how we collect and process your data, please see our Privacy Notice. If you do not have access to the website or would like a hard copy, please contact us.
Recite me
To make use of this function please click on the 3 'A's' button at the bottom left of the website.