Overview
Pre-Application Consultation Events
We recently hosted our second Pre-Application Consultation event in Green Drive Hall in Inverness, which closed out our statutory consultation period for the project.
The materials presented at the event outlined our proposals and our responses to feedback from the first PAC event.
The proejct team will continue to liaise with members of the public and all other stakeholders and respond to any feedback received outwith the formal feedback period.
Details on how to contact the team can be found at the bottom of this page.
About the Project
The project includes the construction of two 275kV point of connections for the Loch na Cathrach Pumped Storage Scheme 450MW at the new Loch na Cathrach 275kV Switching Station. The Loch na Cathrach 275kV Switching Station consists of a new 4-bay 275kV GIS double busbar switching station complete with bus section and two bus couplers.
The Loch na Cathrach 275kV Switching Station will be connected to the existing Knocknagael 275kV Substation by approximately 9km of double circuit 275kV underground cable.
The project also includes enabling and wider works necessary to facilitate the connection of the Loch na Cathrach Storage Scheme onto the 275kV transmission network at the existing Knocknagael 275kV Substation.
Community Engagement
Throughout the life of our projects, we aim to work positively with local communities and keep people informed about what we are doing. This is particularly important when we are developing a proposal and we want to understand what local people think about our plans.
We endeavour to take the time to discuss proposals with local community councils, encourage engagement from the wider community and listen to the feedback we receive.
We will do our best to answer any questions and address issues or concerns that are raised with us.
When our project progresses into construction, we will continue working closely with the local community to ensure that our work has as little impact on the lives of those living and working in the area and as many long term positive effects as possible.
How we’re embracing artificial intelligence (AI)
We intend to use AI to assist our experienced teams in the analysis of your feedback, so we can categorise key points raised more quickly. You can learn more about how we’re utilising AI on this dedicated web page.
Project Updates
Project updates
Documents
Pre-Application Consultation - Feedback Event Materials
-
Loch na Cathrach Underground Cable Route
- Type:
- Date:
- 12 June 2024
- Size:
- 9.5 MB
This map provides information to our stakeholders about the preferred alignment within Loch na Cathrach, produced 26 March 2024.
-
Proposed Knocknagael Substation Layout
- Type:
- Date:
- 12 June 2024
- Size:
- 3.7 MB
This map provides information to our stakeholders about the indicative layout of the site.
-
Loch na Cathrach PAC 2 Consultation Booklet
- Type:
- Date:
- 12 June 2024
- Size:
- 10.4 MB
This document provides information to our stakeholders about the project and was provided during our consultation in June 2024.
Pre-Application Consultation Event Materials April 2024
-
Loch na Cathrach Report on Consultation - Alignment
- Type:
- Date:
- 25 June 2024
- Size:
- 16.9 MB
This Report on Consultation (and associated appendices/maps) documents the consultation process which has been undertaken for the project at corridor, routeing, alignment or substation site selection stage. It describes the key responses received and provides detail on the actions proposed in response to the issues raised.
-
Loch na Cathach PAC 1 Consultation Booklet
- Type:
- Date:
- 12 April 2024
- Size:
- 8.6 MB
This document provides information to our stakeholders about the project and was provided during our consultation in April 2024.
-
Loch na Cathrach Preferred Alignment
- Type:
- Date:
- 12 April 2024
- Size:
- 9.5 MB
This map provides information to our stakeholders about the preferred alignment within Loch na Cathrach, produced 26 March 2024.
-
Substation Extension Layout
- Type:
- Date:
- 12 April 2024
- Size:
- 2.1 MB
This map provides information to our stakeholders about the indicative layout of the site.
-
Red John Consultation Document Site Alignment Bound V03.pdf
- Type:
- Date:
- 26 January 2023
- Size:
- 21.2 MB
-
Red John Consultation Booklet Dec 2022
- Type:
- Date:
- 30 November 2022
- Size:
- 9.9 MB
-
Red John Location Plan Dec 2022
- Type:
- Date:
- 30 November 2022
- Size:
- 473 KB
-
Red John Proposal of Application Notice Dec 2022
- Type:
- Date:
- 30 November 2022
- Size:
- 124.6 KB
-
July 2022 Report on Consultation .pdf
- Type:
- Date:
- 26 October 2022
- Size:
- 26.2 MB
-
April 2022 consultation report
- Type:
- Date:
- 18 September 2022
- Size:
- 36.5 MB
-
April 2022 public consultation booklet
- Type:
- Date:
- 18 September 2022
- Size:
- 3.1 MB
FAQs
FAQs
Recite me