Western Isles HVDC Link Project
- Type:
- Transmission reinforcement
- Location:
- Highland, Western Isles (Na h-Eileanan Siar)
A new subsea cable connecting renewable power and supporting the country's drive to a secure and net zero energy future.
Overview
Status: Project Refinement
Stage 3 of 5
-
Stage 1: Project Assessment: (Completed)
During the Project Assessment stage, we’re committed to evaluating potential project strategies. At this stage, we provide information about the proposed project plans on our website for stakeholders to review and provide feedback on, as well as holding in-person events within the local community demonstrating our collaborative approach to the project's development.
-
Stage 2: Early Development: (Completed)
During Early Development, we concentrate on refining the project details, based on our initial assessment of key environmental, technical, and economic factors to identify the best performing approach. We would like to gain further input from communities through accessible in-person and in some cases online consultations, which are crucial in refining our plans and strategies before advancing to the application stage.
-
Stage 3: Project Refinement: (In progress)
The Project Refinement stage is where we finalise project plans and submit the required planning applications to the relevant planning authorities. Communities and other key stakeholders can provide feedback directly to the appropriate body such as their local council and constituent representatives.
-
Stage 4: Construction Phase:
Within the construction phase we mobilise our workforce, contractors, and necessary equipment to begin construction. We maintain open channels of communication, allowing communities and stakeholders to submit feedback on the construction activities to our dedicated Community Liaison Managers, ensuring ongoing engagement to any thoughts or concerns while we carry out work in the area.
-
Stage 5: Operational Phase:
At this final stage, the project successfully moves into the operational phase, with the surrounding environment restored to its original state or better. Our Community Liaison Mangers continue to be available to address any questions or concerns, ensuring a lasting positive impact and strong community relations even after the construction activities conclude.
About the Project
In order to support the continued growth in onshore and offshore renewables across the north of Scotland, supporting the country's drive towards Net Zero, investment in network infrastructure is needed to connect this renewable power and transport it from source to areas of demand across the country.
The Western Isles is home to some of Scotland’s greatest renewable energy resources, particularly onshore and offshore wind. As the existing Western Isles electricity network is at full capacity, no new electricity generation can connect without significant network reinforcements.
This project is required to connect onshore and offshore wind in and around the Western Isles to the GB transmission system, maximising the significant renewable potential of the Western Isles, adding capacity for new connections and reducing the island's reliance on diesel-powered electricity generation.
Project Elements
- High Voltage Direct Current (HVDC) Converter Station and an Alternating Current (AC) Substation located near Stornoway
- Circa 4km of underground HVDC cable from the new HVDC converter station and AC substation to the landfall at Arnish Point, Stornoway
- 81km of HVDC subsea cable from Arnish Point, Stornoway to Dundonnell on the Scottish mainland
- Circa 80km of onshore underground HVDC cable from Dundonnell to a mainland HVDC Converter Station near Beauly
- A mainland HVDC Converter Station near Beauly

This video outlines how the project contributes to our role in delivering Net Zero.
Other Western Isles Projects
Find out more about Balallan Switching Station
Find out more about Stornoway Windfarm Connection
Pathway to 2030
The Pathway to 2030, published by National Energy System Operator NESO, the electricity system operator for Great Britain, sets the blueprint for the electricity transmission network infrastructure required to enable the forecasted growth in renewable electricity across Great Britain.
The projects identified within the Pathway to 2030 are critical to delivering the UK and Scottish Government’s offshore wind targets. To deliver these targets, we are investing over £10bn to upgrade the network infrastructure across the north of Scotland as the region plays a leading role in the clean energy transition.
As part of this investment, there is a requirement for the Western Isles Connection Project.
How we’re embracing artificial intelligence (AI)
We intend to use AI to assist our experienced teams in the analysis of your feedback, so we can categorise key points raised more quickly. You can learn more about how we’re utilising AI on this dedicated web page.
Project Updates
Featured updates
Featured updates for this project
Project updates
-
Close to 100 new homes for Lewis as SSEN Transmission provides funding for new housing development in Stornoway
SSEN Transmission is helping to deliver nearly 100 new homes for the Western Isles as part of its proposed Lewis Hub project, after committing multi-million-pound funding that will unlock a new housing development near Stornoway Airport.
The announcement has been marked by Deputy First Minster Kate Forbes, who visited the Stornoway Airport Housing Development at Branahuie today to meet representatives of the organisations involved, as well as local apprentices working at the site.
In a major boost for affordable housing provision in the Isle of Lewis, up to 94 new homes are planned for the development, after SSEN Transmission stepped in with significant funding for preparatory work that will enable proposals by local firm CalMax Construction to progress. The new homes are expected to be completed by the end of 2027.
The homes will initially accommodate workers involved in the construction of SSEN Transmission’s Lewis Hub project but will then be made available to the local community, with the majority to be delivered as affordable housing through a partnership between CalMax Construction and Tighean Innse Gall (TIG).
The remaining properties will be sold on the open market, helping to increase the availability of quality housing stock in Lewis, where new-build homes are currently in short supply.
The site at Branahuie is located adjacent to the airport road and has long been earmarked for housing, but a lack of investment has previously stalled development. The arrival of the proposed Lewis Hub project – a key component of the Western Isles HVDC Link – has now provided the catalyst for progress, as SSEN Transmission seeks to house its workforce responsible for constructing the HVDC converter station and AC substation during the project.
The initial funding will unlock the development and allow initial activities to progress, and SSEN Transmission intends to provide further significant, multi-million-pound funding for construction works.
The funding marks one of the first major agreements SSEN Transmission has reached with a housing developer under its housing strategy commitment to support the delivery of 1,000 new homes across the north of Scotland as a legacy of its workforce accommodation requirements. It also demonstrates the economic and social benefits the proposed Lewis Hub and associated connection projects will deliver, with the CalMax development creating and sustaining jobs and apprenticeship opportunities, while also delivering much-needed affordable housing.
-
GI Works for Mainland Cable - Commencing Monday 3 November
There will be GI works taking place on the route for the planned Western Isles HVDC Mainland Cable Project for the next two weeks, starting on 3 November. For the first week (3 – 7 November), there will be a small team working on a borehole at the railway crossing around the area of Contin (Torrachilty) Woods and in the second week (10 – 14 November) the team will be working on a borehole North of the River Orrin (just east of the planned river crossing for the cable).
The GI works are required for HDD Drilling design purposes and will consist of one drilling machine, a low loader and a small team of workers.
If you have further queries please contact the project team via the lt14mainlandcable@sse.com project inbox.
A832 roadworks near Dundonnell – No daytime closures as part of revised planned works
Ahead of a series of stakeholder engagement events later this month, we wanted to provide an update and demonstrate how community feedback is helping to shape our proposed road works on the A832 South of Dundonnell through to Fain Bridge.
We would like to thank everyone who has taken the time to provide their continued feedback to date, which has led to a series of revised proposals detailed below, including confirmation that there will now be no full daytime closures as part of the planned works
To recap, our initial proposal was to:
- have a full daytime road closure, with daily access periods, through the winter season for a period of approximately six to eight months.
We asked for, and received considerable feedback from community councils, local politicians, and businesses, as well as other stakeholders.
Key feedback included:
- Clear indication that daytime closures would cause extensive disruption to communities and services along the A832, that would be extremely difficult to mitigate.
- Questioned the rationale behind the works being undertaken predominantly in the winter season.
- Alternative solutions were suggested, such as completing culvert replacements under single lane closures, as well as night-time work programmes.
With this feedback considered in depth, we challenged our contractor to provide a revised programme.
In light of this, we are now able to confirm that:
- There will be no full daytime closures as part of the planned works.
- All daytime work will be completed under single lane closure with traffic management. We expect we will be doing at least 30 culverts under single-lane closure with traffic management.
- Operation of full night-time closures for several weeks in summer 2026, are planned to allow for the remaining culvert replacement work that cannot be delivered without a full closure.
During this period, the previously proposed diversion via Gairloch will be in place.
Works Duration:
In ruling out full daytime closures, the culvert replacement work is now planned to start in January 2026 and will take until summer 2027.
While this will extend the work programme beyond its initial summer 2026 completion date, we believe our new proposals strike the best possible balance between minimising impacts on the local community, ensuring the safety of road users and our workforce, and delivering improvements to the road as a legacy of the project.
This does not include our ducting and trenching works, which are expected to take around 18 months from summer 2027 and will also be conducted under single lane closure with traffic management.
Further details will be shared at our upcoming events, where the project team will be available to discuss our proposals and answer questions. These will take place on:
Monday 27 October, 6–8pm, Aultbea Hall, Aultbea, Achnasheen, IV22 2HU
Tuesday 28 October, 6–8pm, Badcaul Church, Dundonnell, IV23 2QY
We encourage all members of the local community, and all interested parties to attend the events.
For any further queries please contact our dedicated inbox LT14MainlandCable@sse.com.
GI works for Stornoway GSP - Commencing Monday 13 October
SSEN-Transmission will be carrying out Ground Investigation (GI) Works in the land along the A859 in proximity to the existing GSP Substation and Lochside Arena, Macaulay Farm and South of the Loch Cnoc a Choillich.
These are in relation to the AC Connection projects planned for the area as presented at the information event in Feb 2025 with a subsequent update planned for Nov 2025. Investigation works are required to determine the electrical and structural performance of the ground conditions for future incoming circuits and the GSP redevelopment.
For any enquiries regarding these GI works, please contact us via Kevin.Morrison@sse.com
-
Stakeholder Engagement Events - Early Enabling Works
We are holding a series of stakeholder engagement events in October, following feedback from the local communities most impacted by our initial plan regarding proposed road works on the A832 South of Dundonnell through to Fain Bridge.
- Monday 27 October, 6–8pm, Aultbea Hall, Aultbea, Achnasheen, IV22 2HU
- Tuesday 28 October, 6–8pm, Badcaul Church, Dundonnell, IV23 2QY
These events will provide an update on our early enabling works, where we will share detailed information on what steps we are taking to adjust the execution of the works to best minimise disruption to the local communities and stakeholders.
The project teams will be available to answer questions and discuss our proposals to which we are seeking and welcome feedback.
We encourage all members of the local community and all interested parties to attend the events.
Ecological Survey Work
Our contractors will have consultants visible along the route over the next 2 to 3 months, whilst they carry out essential ecological survey work. This is in advance of the early enabling works which are now planned to start in 2026. For any enquiries regarding these ecological survey works, or our engagement events, please contact us via our dedicated inbox LT14MainlandCable@sse.com.
A832 roadworks near Dundonnell
SSEN Transmission have announced that no work will take place on the A832 until January 2026 at the earliest, and we are continuing to seek solutions that will minimise the impact of the proposed roadworks.
This follows feedback from local communities in response to our call for views on initial proposals affecting a 4.7km stretch of the route, where we plan to replace or upgrade 37 culverts in preparation for the installation of the proposed Western Isles HVDC cable.
We would like to thank everyone who has taken the time to provide their continued feedback to date. Whilst we continue to consider alternative solutions to minimise the impact of these essential works, such as single lane closures or night-time working, we would like to reassure the local community and road users that no works will take place in October and will not start until the new year at the earliest.
A series of in-person engagement sessions will take place in October giving communities a further opportunity to provide feedback on the proposals, and event details will be shared in due course.
Western Isles HVDC mainland cable early works update
We would like to take this opportunity to thank our stakeholders for their continued engagement and feedback regarding the proposed High Voltage Direct Current (HVDC) link between the Western Isles and the Scottish mainland.
We have been inviting views on the traffic restrictions of a 4.7km stretch of the A832 near Dundonnell for enabling works ahead of the installation of the underground cable section of the Western Isles HVDC Link.
In response to the feedback received, we will be making changes to the programme. We are reviewing alternative approaches and will implement measures to minimise disruption during the essential works to replace or upgrade drainage culverts along the cable route. We will continue to seek feedback on these new proposals in due course.
We wish to acknowledge the concerns around the lack of notice regarding our last feedback session – this was never intended to be the only opportunity for stakeholders to express their views, and we apologise this was not made clearer in our communication. We recognise the importance of maintaining regular and transparent communication, and we are committed to ensuring that future engagement is both consistent and proactive.
To that end, we are currently preparing for a series of in-person stakeholder engagement sessions being scheduled for October. These sessions will provide an update on our early enabling works, where we will share detailed information on the execution of the works to best minimise disruption of the public road network.
We remain fully committed to working in partnership with local communities to mitigate disruption wherever possible, and to ensure that all affected parties are fully sighted on the programme before any works commence. We will issue further details on the October sessions in due course, including dates and locations to support participation. In the meantime, we welcome any questions or feedback and remain available to
support stakeholders throughout this process.
Our engineers and supply chain are undertaking significant work to review potential improvements that can be made to mitigate the impact of the enabling works. The areas of road where these culverts are placed present complex technical challenges, including difficult geographical terrain on either side of the carriageway.
We are actively engaging with local amenities and transport providers, delivery companies, health and social care teams along with emergency services to ensure that disruption is kept to an absolute minimum. This includes coordination with healthcare providers, emergency response teams, and other essential services to maintain access and continuity throughout the enabling works. Their input is vital in shaping our traffic management plans and ensuring that measures are in place to support urgent and routine access needs. We are committed to maintaining these critical connections and will continue to work closely with these stakeholders as the programme progresses.
In addition to the enabling works, we are committed to delivering long-term benefits to the local road infrastructure. Beyond the replacement of culverts, we will undertake a series of enhancement measures, including ditch cleaning, rock scaling to remove loose and fallen debris, and the replacement of crash barriers. These improvements are designed to enhance road safety, resilience, and overall condition for all users, leaving a lasting positive legacy following the completion of the works.
We fully acknowledge that the associated diversion route will have a significant impact on local communities and road users. We are therefore committed to working collaboratively with all stakeholders to mitigate this impact wherever possible.
While it is apparent that road closures will be required at points to carry out these works safely, we are actively exploring all feasible alternatives to reduce disruption.
Please be assured that we take all feedback seriously and are working diligently to address the points raised.
A832 temporary road closure information and feedback request
We are proposing a temporary closure of a 5km stretch of the A832 near Dundonnell in two separate phases from late October to spring 2026, and welcome your feedback as we seek to minimise the impact of the temporary closure as far as reasonably possible.
The temporary closure comes as part of permitted development activity in preparation for the installation of the underground cable section of the Western Isles HVDC Link Project, which is vital in helping achieve Scotland and the UK’s clean energy and energy security ambitions. It follows a decades-long campaign for a subsea connection from Lewis to the mainland, to unlock the vast renewable energy potential of the Western Isles.
The proposed underground cable section from Dundonnell to Beauly has followed a detailed project development process, where SSEN Transmission has made every effort to mitigate the impact on local roads, redirecting the original planned route on this basis. As a result of these major revisions, the impact on the road network has been reduced by approximately 50km.
The proposed temporary closure of the A832 is, however, unavoidable, and our contractor RJ McLeod has applied to The Highland Council for a temporary traffic regulation order (TTRO) which would operate over two separate phases from late October to spring 2026. Phase one would be late October to mid-December, and phase two from January to March/April 2026. This would include amnesty periods during the days of operation, details of which are provided in the indicative timetable further below.
The affected area is illustrated here:

The reason for the closure
Safety is our number one priority at SSEN Transmission, and the closure is required to protect the safety of both road users and our workforce as we upgrade or replace 37 culverts along the 5km section of the route. This will allow the cable installation to commence in mid-2026 where we expect a single-lane closure to be in place for the duration of the main works taking place along the A832.
The works will also improve the roads for residents and motorists by:
- providing extensive ditch clearing and removal of recent rock face slips
- scaling of loose rock faces to prevent future slips that may block ditches
- replacement of ageing culvert infrastructure which the council could only replace when they fail, and only via unplanned emergency closures
Indicative timetable of works
Provided the TTRO is approved, phase one is expected to take place from late October until mid-December 2025. Phase two will begin after the new year and is expected to be complete by spring 2026. We will confirm this in writing to homes along the route in due course.
RJ McLeod intends to adopt a fortnightly working pattern of ten days on, four days off. The daily works will be ongoing for around four hours at a time, with reopening times guided where possible by stakeholder feedback. During the four days off period, the road will re-open under a single-lane closure with traffic lights.
Emergency vehicle access (including for the Mountain Rescue Team) will be maintained at all times as well as access for timetabled school transport and local bus services.
A more detailed programme will be made available once the working pattern is confirmed. However, initial indications are that the road will be closed to traffic throughout the day from 7am to 9pm, with daily periods of access during the following busier periods:- 08:00 - 08.45
- 12:30 - 13:30
- 16:30 - 17:30
The road will re-open overnight under a single-lane closure with traffic lights in operation.
How you can help shape our plans
We are making every effort to minimise the impact of the temporary closure as far as reasonably possible, including ongoing liaison with local community councils and stakeholders to understand how it may impact them.
As part of this, we are asking the public to submit feedback on the proposed closure times and access periods, as we seek to build a fuller picture of the needs of communities, organisations, and others who use the route. We ask that you contact us with any queries or feedback at LT14mainlandcable@sse.com.
On Thursday (11 September) from 5pm at Badcaul Church, people will also be able to speak in person to our project team and provide direct feedback.
We hope that you find this information helpful and encourage you to keep in touch with the latest developments by signing up to our project update list via the same email address listed above. -
Marine Licence Variation Application Submitted
SSEN Transmission has submitted a marine licence variation application to the Scottish Government’s Marine Directorate for the Dundonnell to Arnish high voltage direct current (HVDC) project – a strategic development connecting the Fanellan hub near Beauly and a new convertor station hub near Arnish by subsea cable.
Following project developments, it is necessary to include these refinements in the previously consented 2021 Marine Licence.
To support the application an Addendum to the Marine Environmental Appraisal (MEA) which supported the original Marine Licence application has been undertaken. This MEA Addendum describes and assesses potential material changes to the findings of the original MEA, which may result from the project design refinements.
The full Marine Environmental Appraisal Addendum can be found in Documents. -
The Western Isles HVDC Link - Underground Mainland Cable Connection Information Events
We are holding initial information sessions for our proposed 83km High Voltage Direct Current (HVDC) link underground cable, that is planned to connect into our proposed new high voltage AC/DC converter station on the Isle of Lewis and the proposed Fanellan hub near Beauly.
To support the growth in renewable energy developments across the North of Scotland and Islands, which are supporting the drive towards Net Zero, investment in our network infrastructure is needed to connect this power and transport it to areas of demand.
The Western Isles is home to some of Scotland’s greatest renewable energy sources, particularly onshore and offshore wind. As the Western Isles electricity network is at full capacity, no new electricity generation can connect without significant network reinforcements.
The Western Isles HVDC Link - Underground Mainland Cable Connection is key to accommodating a significant increase in new sources of power generation.
The information events will be held on:
Tuesday 10 June, 12.30–3.30pm
Dundonell Hotel, IV23 2QR
Wednesday 11 June, 3.30–6.30pm
Contin Village Hall, IV14 9ES
Thursday 12 June, 3–6.30pm
Phipps Hall, IV4 7EH
The project teams will be available to answer questions and discuss our proposals to which we are seeking and welcome feedback.
We encourage all members of the local community and all interested parties to attend the event.
If you are unable to attend, the consultation booklet can be found in Documents.Peat Restoration Walk Through Survey Tuesday 20 May 2025
On Tuesday 20 May 2025 a small team from McGowans will be visiting the Marybank area (Creed North) to complete a visual only inspection of the success levels of Peat restoration works that were completed on the previously identified site for the Lewis hub, and now have been in situ now for 12 months.
If you have any queries about this work, please do not hesitate to contact Community Liaison Manager Kevin Morrison on kevin.morrison@sse.com. -
Western Isles HVDC week commencing 14th April 2025
SSEN Transmission has started Ground Investigation works along the underground cable route for the Western Isles HVDC this week commencing 14th April 2025 for approximately 18 weeks along the Purple line on the map below.

There will be between 3 to 4 squads working along the route at any one time and will adopt an initial shift pattern of a 5- day week with the potential to increase to a 12-day fortnight. The hours of work will fall between 08:00 -18:00.
The duration of time at each location along the route will be dependent on how deep the trial pit/borehole is, but a rough estimation is between half a day for trial pits and up to two days for boreholes.
Further information is available on this dedicated web page.
If you have any queries about this work, please do not hesitate to contact our Community Liaison Managers by phone or email.
Yours faithfully
Kevin Morrison Sally Cooper
Community Liaison Manager Community Liaison Manager
Email: kevin.morrison@sse.com Email: sally.cooper@sse.com
Mob: 07586 237814 Mob: 07918 470281 -
Planned Ground Investigation Restoration Works on Arnish Moor
Reinstatement works from previous Ground Investigation (GI) will begin on the week commencing Monday 5th May for a 2 to 3 week period. This will then be followed by some additional GI works for the two weeks preceding this. Welfare units are set up and some traffic management will be situated on the A859 at Lochside arena. The works will involve one or two excavators working on Arnish moor. Additional GI will be focused excavation for trial holes, these will be inspected and then backfilled accordingly. -
We're here to lend a helping hand
We are committed to supporting the communities in the north of Scotland where we operate, both now and in the future. As part of our ongoing efforts to make a difference and have a positive impact on local communities, we are proud to offer volunteering days to local groups and charities, particularly in the areas that host our electricity infrastructure or where our proposed projects are located.
This month, we’re excited to announce the launch of our new Volunteering Webpage, designed to make it easier for local communities to request volunteering support from us. To request our help, simply complete the ‘Volunteering Nomination Form’ linked at the bottom of our new webpage. Please note, as our team works on a voluntary basis, it may take us some time to coordinate our people and match them with opportunities. We kindly ask for your patience as we work to keep up with volunteering demand.
Thank you for considering SSEN Transmission as a partner in your community efforts. Together, we can leave a positive, lasting legacy and help transform communities across the north of Scotland.
Western Isles businesses invited to Lewis Hub ‘Meet the Buyer’ event
Local businesses in the Western Isles are being invited to an event taking place later this month, highlighting the range of opportunities available through the proposed Lewis Hub HVDC substation and converter station project.
The ‘Meet the Buyer’ event takes place at the Cabarfeidh Hotel in Stornoway on Thursday 27 February, from 3pm – 6pm. It will allow local businesses to engage with the project’s principal contractors and discuss local supply chain opportunities.
The Lewis Hub is an essential part of the Western Isles Connection Project that will establish a new subsea HVDC link between Lewis and the mainland. Located at Arnish Moor near Stornoway, its construction will offer supply chain opportunities in a variety of areas from civil engineering, haulage and landscaping, to waste management, security and office services.
Kevin Morrison, SSEN Transmission’s Community Liaison Manager for the Lewis Hub project, said: “We are committed to supporting local businesses and maximising opportunities to employ local staff and contractors where possible, and our Meet the Buyer event is an opportunity for businesses to connect with our principal contractors to explore how they might complement the project’s specialist construction teams.
“The project has the potential to create a wide range of opportunities in a variety of areas, and we’re pleased to be able to offer this opportunity for businesses to engage. As well as our principal contractors, we’ll also have representatives from Highlands and Islands Enterprise and the University of the Highlands and Islands on hand to help with enquiries relating to business support and training opportunities.
“The project continues to have widespread local support reflecting its importance to the development of renewable energy in and around the Western Isles and the significant economic and job opportunities it will unlock – we encourage local businesses to come along to our event and find out more about the opportunities available.”
Please email the Project inbox lt14lewishub@sse.com if you have any further questions regarding the event. -
Notification of ground investigation works and environmental surveys on mainland cable route over the coming months
As part of the proposed Western Isles HVDC project SSEN Transmission are required to carry out further Ground Investigation (GI) and environmental survey works along the mainland cable route which will connect the proposed substation/converter station project on Lewis to the proposed substation/converter station project at Fanellan near Beauly.
The GI work is due to start w/c 27th January off a section of the A832 near Dundonnell and is expected to take approximately 2 weeks. Traffic management will be in place and there may be short delays to your journey. The works will involve the use of specialist plant and equipment to determine underlying ground conditions. Further ground investigations will be carried out on different sections of the route over the coming months.
We apologise for any inconvenience these may cause.
Please see the map below which shows the mainland cable route in green.
The environmental survey works are due to commence shortly and will involve non-intrusive visual inspection of the whole route by small teams of environmental specialists on foot. These works are expected to take 2 weeks.
If you have any queries about this work, please do not hesitate to contact the Community Liaison Managers for this project. -
Lewis Hub Initial GI Works Completed
SSEN-Transmission would like to inform stakeholders that the site Geotechnical Investigation (GI) works on the Arnish Moor site has now been completed and the team is currently demobilising from the site.
An assessment of the condition of the site will be undertaken by one of SSEN-Transmissions consultants and appropriate restoration works will be commissioned where necessary. Further investigation works are also currently being evaluated for the site. These are anticipated to take place in the spring of 2025.
Lewis Hub 400kV Substation and High Voltage Direct Current (HVDC) Converter Station: Stornoway Event
We are pleased to be hosting a second public Pre-Application Consultation (PAC) event on our proposed new substation and converter station on Arnish Moor, following our initial event in September 2024 and feedback period which closed on the 17 October 2024. Any additional comments received following the second consultation event will be collected for the Pre-Application Consultation Report as well as those comments received at the first PAC event. The closing date for this feedback will be the 28 November 2024.
We are holding this event to present our proposed design for planning submission, following feedback received from the first PAC event and ongoing design developments. We will also present our responses to feedback received as part of the statutory consultation, which is required for major and national planning applications.
We invite all interested parties to attend, meet the team, and share your views.
The event will be held on:
Date: 14 November 2024
Time: 3pm-7pm
Venue: Cabarfeidh Hotel, Stornoway, HS1 2EUIf you are unable to attend the public event all the material that will be on display will be available to be downloaded from the Documents section of the project webpage.
Please let us know if you require information in an adapted format such as paper copy, large print or braille and we will work with you to accommodate your preferences. We are happy to accommodate all reasonable requests for adapted communications. -
SSEN Transmission Ground Investigations for the New Western Isles Connection Project
SSEN Transmission would like to inform the public that initial ground investigation works are being undertaken as part of the development of the proposed new Lewis Hub area for the Western Isles Converter station as shown on the map below.

The works involve digging and drilling a series of trial pits and boreholes to obtain a detailed picture of ground conditions and geology. During the works, you may notice increased levels of traffic on the access tracks to the site, with some heavy plant and machinery being transported to and from the site at the start and end of the works.
Overseeing the works are the SSEN Transmission project team, together with specialist supervision from ecologists and archaeologists who will ensure the works do not negatively impact local wildlife or archaeological assets (both known and unknown). The work will be undertaken during daylight hours and no work will take place on Sundays. The duration of the work will be approximately ten weeks. The works are due to commence during the week commencing Monday 02 September 2024.
The project is in the early stages of development and the investigation works are a key part of this process. The results of these investigations will provide project teams with valuable information to help inform the site selection process.
We apologise in advance for any inconvenience and if you require any further information, please contact the Western Isles Community Liaison Manager on kevin.morrison@sse.com or visit the Western Isles Connection Project webpage.
-
Lewis Hub 400kV Substation and High Voltage Direct Current (HVDC) Converter Station: Stornoway Event
We are pleased to be hosting the first of two rounds of statutory pre-application consultation events for our proposed new Lewis Hub 400kV Substation and High Voltage Direct Current (HVDC) Converter station on Arnish Moor. The pre-application process is a key first step in the Town and Country planning process for national planning applications.
At this event we will be sharing the new proposed site location, layout details and visualisations as well as information about the connections into the proposed Arnish Moor site. The project teams will be available to answer questions and discuss our proposals to which we are seeking and welcome feedback.
We invite all interested parties to attend, meet the team, and share your views.
The event will be held on:
Date: 05 September 2024
Time: 3pm-7pm
Venue: Cabarfeidh Hotel, Stornoway HS1 2EUIf you are unable to attend the public event all the material that will be on display can be downloaded here.
-
Ground Investigation Works
SSEN Transmission is about to start Ground Investigation works along the underground cable route for the Western Isles HVDC starting the week commencing the 27th of May 2024 for approximately 12 weeks along the A835 and A832. There will be between 3 to 4 squads working along the route at any one time and a shift pattern of 12-day fortnight from 08:00 -18:00 or till daylight hours allow.
The duration of time at each location along the route will be dependent on how deep the trial pit/borehole is, but a rough estimation is between half a day and up to three days.
Cable Route Maps available here. -
Western Isles Project Update
Remediation works on the Creed North site are due to start towards the end of April, the duration of this work will be approximately 8-10 weeks weather dependent.
Works are anticipated to commence on week commencing the 22/04/2024 and are expected to last until 28/06/2024, the team will mobilise from week commencing the 15/04/2024, and the team will use a compound area within the Breedon’s yard for the necessary site offices and storage.
A brief overview of the works:
The works will be delivered using a variety of techniques. The following points highlight some of the approaches to tackling different sections of the site:
Flatter areas of the site with good turf availability – these areas would be shaped back to the original ground profile, utilising nearby available turf where possible. All turf borrow locations would be fully re-instated.
Flatter areas of the site with poor turf availability – these areas would be treated similarly to above, however, we would either use a tracked dumper to import donor turf from further afield (say up to 40m away) or accept that is only limited returfing could be undertaken. If only limited turfing could be undertaken, we would checkerboard or spot turf the bare areas, recovery would be slower, but the area should recover over time.
Steeper slopes – there are steeper areas with tracking lines up the hill from the hard standing by the river intake. This section of the project will require a higher level of intervention. One of the priorities here will be managing water and ensuring that pathways for water do not establish through the exposed peat, which is highly erodible. Works will be undertaken to cast water off the bare areas and away on to open ground.
The area by the water intake on the river – this section of work requires careful planning to ensure there is no concentrated flow of silt-laden water reaching the watercourse. The main outcome will be to hold any run-off on the land and allow this to soak in. In addition, importing material to bring the level of the access road and hard standing up and “high and dry” of standing water may be beneficial.
-
Work ongoing to explore alternative potential site for new Lewis HVDC convertor station and substation
- SSEN Transmission confirm it is no longer progressing Creed North substation site
SSEN Transmission can confirm that its Western Isles HVDC Connector Project team are no longer actively progressing the Creed North site it previously consulted on for its proposed new HVDC Convertor Station and AC Substation, a key component for the Western Isles HVDC subsea link.
“As well as the Trust’s continued support, other stakeholders must also play their part to enabling SSEN Transmission to find a more suitable solution.”
Following consultation on the proposed substation site last year, SSEN Transmission has received feedback from a range of local stakeholders, including the landowner, the Stornoway Trust; elected members; Marybank and Maryhill Community Association; the Stornoway Historical Society; the Stornoway Angling Association; local crofters and other local community interest groups and members.
SSEN Transmission welcomes the widespread support for the project need and in recognising the strength of feeling amongst the local community against the proposed siting of the substation at the Creed North location, SSEN Transmission is now actively exploring alternative sites. This work is ongoing with an update on the extended site selection process expected in the coming weeks.
Colin Bell, Lead Project Manager, said:
“Following feedback from a range of individuals and groups we can confirm that we are no longer actively progressing our previously identified preferred convertor station and substation site at Creed North.7
“We would like to thank all stakeholders who kindly took the time to constructively provide their feedback and hope that our commitment to explore alternative sites helps address local concerns.
“Work to identify an alternative potential site is ongoing and to help inform this site selection process, our teams will continue to balance key environmental, technical and construction constraints, whilst seeking to minimise and where possible mitigate community and landscape impacts.
“We remain fully committed to engaging constructively with all stakeholders and look forward to presenting an update on our site selection process for further public consultation in the coming months.”
Iain MacIver, Estate Factor at The Stornoway Trust, said:
“SSEN Transmission’s pledge to seek a more suitable location for the long-awaited convertor station is warmly welcomed and gratefully appreciated by the Trust.
“Dependent on our Island’s renewable energy aspirations is the timely delivery of the key component on which the future of so many projects rely. -
SSEN Transmission sets out next steps for Pathway to 2030 network developments
We have announced our next steps for our Pathway to 2030 programme of projects. We would like to thank everyone who has engaged with our teams and kindly taken the time to respond to our consultations.
Full details of the announcement can be found here:
Next steps for Pathway to 2030 -
Arnish Feedback Form June 2022
Feedback form from public consultation in June 2022
Western Isles Project Update
Pathway to 2030’ publication, the Electricity System Operator, National Grid ESO, has confirmed the requirement for a 1.8GW HVDC subsea link from the Western Isles to the north of Scotland mainland. The new link, which has been identified as one of the key investments across GB that is required to meet 2030 offshore wind targets, marks a major step forward in unlocking the renewable energy potential of the Western Isles.
The 1.8GW link will be sufficient to accommodate all known onshore and offshore wind in and around the Western Isles, including the two ScotWind sites in closest proximity to the islands, with some additional capacity to support future renewable generation developments. This new link will therefore replace SSEN Transmission’s previous proposal for a 600MW HVDC subsea link.
Constructing a link of this scale will deliver a more economical solution that will minimise environmental impacts, as well as maximising the benefits for consumers, communities, and renewable generation developers. This includes an expected significant reduction in Transmission Network Use of System Charges (TNUoS) for connecting renewable generation developers. This investment will also strengthen the security of supply for homes and businesses on the islands.
Given the extent of project development that has already been undertaken on connecting the Western Isles, the foundations are already in place to enable the timely delivery of this new project. SSEN Transmission will now explore options to accelerate the development of the 1.8GW link in advance of its current 2030 delivery date.
SSEN Transmission has already commenced a programme of engagement with its contracted customers, its supply chain, and wider stakeholders, including the Western Isles Council, UK, and Scottish Governments and elected members, to help inform the accelerated development and timely delivery of the 1.8GW link.
As part of this engagement, SSEN Transmission is working with Ofgem on the process for regulatory approvals for the 1.8GW link as part of the ‘Pathway to 2030’ network requirements set out by the ESO.
-
Western Isles Notice of Interest Form
In March 2018, SSEN held a town hall meeting in Stornoway with local developers to seek feedback on expected levels of generation capacity via a notice of interest form. If you are a local developer, and would like to share details of your plans with us please fill out the notice of interest form using the link above. Please note that this is not an application for a connection. If you have any queries about the form please contact westernisles@sse.com. Alternatively if you wish to make a formal application to connect please visit: https://www.ssepd.co.uk/Connections/
Pre-application consultation events
Great turnout, over 30 members of the public and stakeholders were welcomed at The Cabarfeidh Hotel in Stornoway on Monday to talk to the project team at the pre-application event for the marine cable due to be submitted in April 2018. Further events are being held at:The Argyle Hotel Ullapool - Wednesday 14th March 3pm - 7pm Badcaul Primary School - Thursday 15th March 3pm - 7pm -
Consultation on treatment of non-mainland GB onshore wind projects
We have today responded to the UK Government consultation on treatment of non-mainland GB onshore wind projects, to read our response please go to the ‘Project documentation’ section of the project website -
Project Tender Update
Scottish Hydro Electric Transmission is currently undertaking a competitive tender exercise for the whole of the project and is working towards identifying a preferred Principal Contractor by the end of March 2017 with the overall project delivery currently anticipated to be by the end of September 2021.
Documents
Project Documents
-
Mainland Cable Enabling Works Presentation - October 2025
- Type:
- Date:
- 30 October 2025
- Size:
- 1.5 MB
This document provides an update to our stakeholders about the enabling works for the mainland cable, produced for our engagement sessions during October 2025.
-
Underground Cable Route Map - Summer 2025.jpg- Type:
- Image
- Date:
- 09 October 2025
- Size:
- 4.9 MB
-
Underground Cable Route Map - Sheet 1 - Fanellan to Contin.jpg- Type:
- Image
- Date:
- 09 October 2025
- Size:
- 6.9 MB
-
Underground Cable Route Map - Sheet 2 - Contin to Silverbridge.jpg- Type:
- Image
- Date:
- 09 October 2025
- Size:
- 6.8 MB
-
Underground Cable Route Map - Sheet 3 - Silverbridge to Blackbridge.jpg- Type:
- Image
- Date:
- 09 October 2025
- Size:
- 6.5 MB
-
Underground Cable Route Map - Sheet 4 - Abhainn Culeag Hydro to Fain Bridge.jpg- Type:
- Image
- Date:
- 09 October 2025
- Size:
- 6 MB
-
Underground Cable Route Map - Sheet 5 - Abhainn Culeag Hydro to Fain Bridge.jpg- Type:
- Image
- Date:
- 09 October 2025
- Size:
- 7 MB
-
Underground Cable Route Map - Sheet 6 - Fair Bridge to Dundonnell.jpg- Type:
- Image
- Date:
- 09 October 2025
- Size:
- 6.2 MB
-
Western Isles HVDC Link - MEA Addendum
- Type:
- Date:
- 02 July 2025
- Size:
- 6.8 MB
This Marine Environmental Appraisal (MEA) Addendum describes and assesses potential material changes to the findings of the original MEA, which may result from the project design refinements.
-
Hvdc Underground Cable Consultation Booklet
- Type:
- Date:
- 28 May 2025
- Size:
- 22 MB
This material provides information to our stakeholders about the project and June 2025 information events.
-
Western Isles PAC 2 Consultation Booklet
- Type:
- Date:
- 31 October 2024
- Size:
- 18.2 MB
This document provides information to our stakeholders about the project and was provided during our consultation in November 2024.
-
Western Isles PAC 1 Consultation Booklet - Gaelic
- Type:
- Date:
- 30 August 2024
- Size:
- 13.2 MB
Gaelic version of the Site Selection Consultation Document (and associated appendices/maps) explaining the project need and summarises the process which has been followed to arrive at the optimal site. It forms part of the consultation exercise which provides all interested parties with the opportunity to provide feedback.
-
Western Isles PAC 1 Consultation Booklet
- Type:
- Date:
- 22 August 2024
- Size:
- 13.5 MB
This Site Selection Consultation Document (and associated appendices/maps) explains the project need and summarises the process which has been followed to arrive at the optimal site. It forms part of the consultation exercise which provides all interested parties with the opportunity to provide feedback.
-
Connections into Fanellan and Permanent Requirements Layout Plan
- Type:
- Date:
- 10 June 2024
- Size:
- 2.7 MB
These maps provide information to our stakeholders about the connections into the proposed Fanellan site.
-
Western Isles Handout
- Type:
- Date:
- 10 June 2024
- Size:
- 6.7 MB
This document provides information to our stakeholders about the project in 2024.
-
Cable Route Maps
- Type:
- Date:
- 22 May 2024
- Size:
- 7.4 MB
These maps provide information to our stakeholders about the cable route, produced May 2024.
-
Western Isles Connection - Consultation and Information Booklet - November 2023
- Type:
- Date:
- 30 October 2023
- Size:
- 15.4 MB
This document provides information to our stakeholders about the project and was provided during our consultation in November 2023.
-
Western Isles Mailer - November 2023
- Type:
- Date:
- 24 October 2023
- Size:
- 78.9 KB
This document provides information to our stakeholders about our consultation events in November 2023.
-
Western Isles Mailer
- Type:
- Date:
- 15 August 2023
- Size:
- 430 KB
This document provides information to our stakeholders about our consultation events in April 2023.
-
Western Isles Consultation Booklet
- Type:
- Date:
- 15 April 2023
- Size:
- 18.2 MB
This document provides information to our stakeholders about the project and was provided during our consultation in April 2023.
-
Arnish Booklet
- Type:
- Date:
- 18 September 2022
- Size:
- 3.5 MB
This document provides information to our stakeholders about the project and was provided during our consultation in June 2022.
Environmental Impact Assessment Report
-
EIAR Volume 1 - Non-Technnical Summary.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 2.2 MB
-
EIAR Volume 2 - Main Report.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 4.5 MB
-
EIAR Volume 3a - Figures - Figure 11.1.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 1.8 MB
-
EIAR Volume 3a - Figures - Figures 12.1-12.2.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 2.6 MB
-
EIAR Volume 3a - Figures - Figures 5.1-5.6_Optimized.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 3.6 MB
-
EIAR Volume 3a - Figures - Figures 6.1-6.2.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 4.2 MB
-
EIAR Volume 3a - Figures - Figures 8.1-8.5_Optimized.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 1.8 MB
-
EIAR Volume 3a - Figures - Figures 9.1-9.4.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 3.4 MB
-
EIAR Volume 3a - Figures- Figures 1.1-4.1_Optimized.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 2.6 MB
-
EIAR Volume 3a - Figures- Figures 7.1-7.4_Optimized.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 1.2 MB
-
Lewis Hub_EIAR Vol 3b_Visualisations_Figs5.11-5.13.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 7 MB
-
Lewis Hub_EIAR Vol 3b_Visualisations_Figs5.14-5.16.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 8.9 MB
-
Lewis Hub_EIAR Vol 3b_Visualisations_Figs5.17-5.23.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 8.1 MB
-
Lewis Hub_EIAR Vol 3b_Visualisations_Figs5.24-6.4.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 3.9 MB
-
Lewis Hub_EIAR Vol 3b_Visualisations_Figs5.7-5.10.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 8.2 MB
-
EIAR Volume 4 - Technical Appendices - TA 1.1.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 572.1 KB
-
EIAR Volume 4 - Technical Appendices - TA 10.1 - Part1.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 8.4 MB
-
EIAR Volume 4 - Technical Appendices - TA 10.1 - Part2.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 8 MB
-
EIAR Volume 4 - Technical Appendices - TA 10.1 - Part3.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 3.4 MB
-
EIAR Volume 4 - Technical Appendices - TA 10.2.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 8 MB
-
EIAR Volume 4 - Technical Appendices - TA 10.3 - Part1.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 1.9 MB
-
EIAR Volume 4 - Technical Appendices - TA 10.3 - Part2.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 12.8 MB
-
EIAR Volume 4 - Technical Appendices - TA 10.4.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 116.2 KB
-
EIAR Volume 4 - Technical Appendices - TA 10.5.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 95.3 KB
-
EIAR Volume 4 - Technical Appendices - TA 11.1-11.10.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 3.1 MB
-
EIAR Volume 4 - Technical Appendices - TA 12.1-12.2.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 622.8 KB
-
EIAR Volume 4 - Technical Appendices - TA 2.1.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 6.3 MB
-
EIAR Volume 4 - Technical Appendices - TA 2.2.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 5.4 MB
-
EIAR Volume 4 - Technical Appendices - TA 2.3.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 5.4 MB
-
EIAR Volume 4 - Technical Appendices - TA 4.1-4.3A Opt.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 7.9 MB
-
EIAR Volume 4 - Technical Appendices - TA 5.1-5.3.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 2 MB
-
EIAR Volume 4 - Technical Appendices - TA 5.4 - Part1.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 7.2 MB
-
EIAR Volume 4 - Technical Appendices - TA 5.4 - Part2.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 7.1 MB
-
EIAR Volume 4 - Technical Appendices - TA 5.4 - Part3.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 6.4 MB
-
EIAR Volume 4 - Technical Appendices - TA 5.5.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 6.2 MB
-
EIAR Volume 4 - Technical Appendices - TA 6.1-6.4.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 795.2 KB
-
EIAR Volume 4 - Technical Appendices - TA 7.1-7.4 .pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 550.2 KB
-
EIAR Volume 4 - Technical Appendices - TA 8.1.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 182.2 KB
-
EIAR Volume 4 - Technical Appendices - TA 9.1-9.2.pdf
- Type:
- Date:
- 14 March 2025
- Size:
- 5.4 MB
Pathway to 2030 Projects - Additional Information
-
How SSEN Transmission Earn Our Income
- Type:
- Date:
- 07 August 2025
- Size:
- 139.8 KB
As a natural monopoly, we are closely regulated by the GB energy regulator, Ofgem, who sets how much revenue we are allowed to earn for constructing, maintaining and renovating the transmission network in the north of Scotland.
-
Early Careers
- Type:
- Date:
- 25 July 2025
- Size:
- 4.1 MB
To reach net zero by 2050, we’re acting now. And we need bright talent, fresh ideas, and people who want to make a difference to help power the change. This document provides information about our Graduate Programme, Apprentice and Trainee Engineering schemes and Summer Placements.
-
Delivering Legacy Benefits through Pathway to 2030 Projects
- Type:
- Date:
- 25 July 2025
- Size:
- 14.5 MB
This document details how this investment programme will ensure a reliable supply of electricity, lead to thousands of jobs across the region, a programme of skills development ensuring a workforce fit for the future and place multi-million-pound contracts with the local supply chain benefitting local communities.
-
Working with landowners and occupiers
- Type:
- Date:
- 17 July 2025
- Size:
- 12.6 MB
We recognise landowners and occupiers as key stakeholders in the development of our projects. This document details what happens if a voluntary agreement cannot be reached, concerns about impact on properties, following legal frameworks, biosecurity, and irrigation.
-
What to expect during the delivery of our projects
- Type:
- Date:
- 19 February 2025
- Size:
- 11 MB
Over the coming months, SSEN Transmission will be submitting a number of planning applications for consent to construct our 'Pathway to 2030' projects. This document is designed to provide information on what communities and stakeholders can expect during the pre-planning consent and delivery phases of our projects.
-
HVDC vs HVAC
- Type:
- Date:
- 11 February 2025
- Size:
- 2 MB
-
Biodiversity Net Gain
- Type:
- Date:
- 11 February 2025
- Size:
- 19.9 MB
We will always look to minimise the potential impacts from our activities and achieve Biodiversity Net Gain (BNG). This document explains our approach and includes some examples of initiatives carried out at our sites.
-
Community Benefits
- Type:
- Date:
- 11 February 2025
- Size:
- 1011.6 KB
Find out more about our Community Benefit Fund via this document.
-
Delivering a Positive Environmental Legacy
- Type:
- Date:
- 11 February 2025
- Size:
- 6.4 MB
This booklet describes our approach to leaving a positive environmental legacy, including our marine biodiversity approach.
-
Electric and Magnetic Fields (EMFs)
- Type:
- Date:
- 11 February 2025
- Size:
- 18.5 MB
This document describes how we develop, build and operate our infrastructure to met all health and safety legislation and guidance in respect of EMFs, protecting us all and keeping our network safe for the public.
-
Pathway to 2030 - Tower Crossings
- Type:
- Date:
- 11 February 2025
- Size:
- 5 MB
In this document you can learn more about the composition of our 400kV towers, and the approach we take when our overhead lines must cross existing assets.
-
Planning Applications under the Town and Country Planning (Scotland) Act 1997
- Type:
- Date:
- 11 February 2025
- Size:
- 3.2 MB
The main legislation that governs the consenting of our substation and converter station projects is the Town and Country Planning (Scotland) Act 1997. This document describes the pre-application process including consultation, our environmental assessments and our planning application submission and how this is determined.
-
Protecting Private Water Supplies
- Type:
- Date:
- 11 February 2025
- Size:
- 7.2 MB
Construction works and site investigation have the potential to impact on private water supplies (PWS) and we know that this can be a concern to occupants. This document outlines the activities we undertake to identify and protect PWS.
-
Routeing Overhead Lines
- Type:
- Date:
- 11 February 2025
- Size:
- 3.1 MB
-
The challenges with undergrounding at 400kV
- Type:
- Date:
- 11 February 2025
- Size:
- 2.9 MB
We are often asked why our new Pathway to 2030 400kV connection projects cannot all be delivered via an underground cable instead of an overhead line. This paper explores some of the technical and engineering, operational, environmental and economic challenges associated with underground cabling which need to be carefully considered.
-
Updated Sustainability Strategy
- Type:
- Date:
- 11 February 2025
- Size:
- 10.6 MB
-
Why the Pathway to 2030 projects require both onshore and offshore solutions
- Type:
- Date:
- 11 February 2025
- Size:
- 2.5 MB
We are regularly asked why our Pathway to 2030 transmission network upgrades cannot all be delivered offshore via subsea links. This document explains some of the many factors that drive the need for both onshore and offshore solutions.
-
How Stakeholder Feedback Influences Our Proposals
- Type:
- Date:
- 18 September 2024
- Size:
- 1.1 MB
The document outlines how stakeholder feedback influences our decisions
-
The Section 37 Consent Process
- Type:
- Date:
- 13 May 2024
- Size:
- 1.7 MB
The legislation governing the consenting of overhead line projects in Scotland is the Electricity Act 1989. Applications for consent to construct and operate new overhead lines are made under Section 37 of this Act and are referred to as “Section 37 Consents”. You can find out more about this process in this document.
-
Pathway to 2030 - Why are these projects needed
- Type:
- Date:
- 13 May 2024
- Size:
- 4 MB
We receive a lot of queries about the need for our Pathway to 2030 projects. This document sets out some of the policies and targets driving the need for investment in new clean power and the electricity transmission network that is required to enable this. It also explains the electricity network planning processes that have established the need for these reinforcements.
FAQs
Who we are
-
SSEN Transmission operates, maintains, and improves the high voltage electricity transmission network in the north of Scotland.
Our network extends over a quarter of the UK’s land mass and some of its most challenging terrain. This area has a lot of renewable energy potential such as wind, solar, hydro and marine power.
We work with the National Grid Electricity Systems Operator so that electricity generated in the Highlands and Islands can reach homes and businesses across Britain.
-
SSEN Transmission is owned 75% by SSE plc and 25% by Ontario Teachers’ Pension Plan.
-
We are closely regulated by the independent energy regulator, Ofgem, for the work we do constructing, operating, and maintaining the transmission network in the north of Scotland.
The costs of constructing, operating, and maintaining the transmission network are shared between all those using the transmission system, including generation developers and electricity consumers.
Ofgem set how much money we invest, what return we make on this investment and how these costs are recovered from users of the electricity transmission system.
About the Pathway to 2030 projects
-
What is Pathway to 2030
The Pathway to 2030 is a series of projects to increase capacity of the transmission network in northern Scotland. It is part of a national effort to upgrade power lines across Great Britain to connect and transport renewable electricity, especially from offshore wind farms.These projects contribute towards meeting climate goals and renewable targets, ensuring energy security and supporting Scottish and UK Government targets for a just transition to a net zero future.
Why is it needed?
- Addressing Climate Change: The UK and Scottish Government have ambitious targets to combat climate change and guarantee a secure and reliable supply of energy. The UK is aiming for 50 gigawatts (GW)* of offshore wind-generated electricity by 2030. Our Pathway to 2030 projects have been identified as required to help achieve such targets by delivering the vital infrastructure required.
*For background, A GW is a unit of measurement of electrical power. It is equal to one billion watts. - Promoting Energy Independence: In 2022, the UK Government set out a strategy to reduce dependence on volatile global gas markets, moving to local, sustainable electricity sources instead. Establishing the necessary infrastructure for this is critical.
- Planning for future need: Experts with the National Grid Electricity System Operator carry out extensive analysis and research to predict the UK’s future energy needs. This information is then carefully considered to guide infrastructure upgrade decisions.
- Approved by Ofgem: Britain's independent energy regulator, Ofgem, granted approval for these projects in December 2022 as part of its strategy for accelerated network upgrades.
More information explaining the need for these projects can be found here, for more information on the Government policies that underpin this need and how the need has been identified and assessed please read our information leaflet.
- Addressing Climate Change: The UK and Scottish Government have ambitious targets to combat climate change and guarantee a secure and reliable supply of energy. The UK is aiming for 50 gigawatts (GW)* of offshore wind-generated electricity by 2030. Our Pathway to 2030 projects have been identified as required to help achieve such targets by delivering the vital infrastructure required.
-
To deliver energy security and net zero, further additional investment in new low carbon electricity generation and the enabling electricity transmission network infrastructure will be required across Great Britian, including the north of Scotland.
In March 2024, the independent National Energy System Operator’s (NESO) published its ‘Beyond 2030’ report, which confirmed the need for several new, replacement and upgraded transmission infrastructure projects in the north of Scotland. In December 2024, Ofgem approved the next phase of regulatory funding to take these projects through the development phase.
These additional investments will soon be subject to extensive public consultation and engagement to help inform their development, with early consultation and engagement expected to take place within 2025. Additional regional investments are also likely to be required to deliver the UK Government's Clean Power 2030 ambition. Further details on these will be communicated once the need and scope for these investments has been established.
More details on what this means for projects in the north of Scotland are included on our website here
-
SSEN Transmission is responsible for where and how the high voltage transmission network operates in the north of Scotland. However, we don't determine where energy is generated – nor where it is needed.
We have a legal obligation to provide electricity generators with access to our network, so that the electricity they generate can be transported across GB to meet the energy demand of homes and businesses.
The north of Scotland is rich in renewable energy, especially wind, water, and marine sources meaning this region is vital for the UK and Scotland's climate goals. Our area covers a quarter of the UK landmass and will be crucial in the move towards a low carbon future.
Our approach to routeing and public consultation
-
Our approach to optioneering (routes for overhead lines or sites for substations) is underpinned by our statutory obligations, as set out in the Electricity Act Schedule 9, to ‘develop and maintain an efficient, coordinated and economical electricity transmission system’. Having regard to the “desirability of preserving the natural beauty, of conserving flora, fauna and geological and physiographical features of special interest and protecting sites, buildings and objects of architectural, historic or archaeological interest; and do what we reasonably can to mitigate any effect which the proposals would have on the natural beauty of the countryside or on any such flora, fauna, features, sites buildings or objects’.
As a result, our optioneering process seeks to balance technical and cost considerations with environmental considerations. To select a proposed option which is economically viable, technically feasible, minimises impacts on important resources or features of the environment and reduces disturbance to those living in it, working in it, visiting it or using it for recreational purposes. The option must also be capable of being granted consent by either the Scottish Government (in the case of overhead line projects) or local planning authorities (in the case of substation projects).
To do this we consider specific topic areas within the environmental, technical and cost categories and assess each in terms of the potential for the option to be constrained. We allocate a Red/Amber/Green (RAG) rating to each topic to highlight where potential issues may be present and use this to help compare the different options. The appraisal seeks to compare the wider implications of each option on those topics (both individually and combined) and reach a reasoned conclusion, on balance across all topics, as to the ‘preferred option’ to take forward.
Any weighting of certain criteria as being of more importance than other criteria would depend on project specific considerations. For example, if a particular technical or environmental constraint has been identified as a priority consideration through stakeholder engagement (or engineering specification) and is unable to be overcome, this will inevitably carry greater weight in the comparison of options which may otherwise contain constraint that can be easily designed out or mitigated.
We follow this comparative approach through stages of refinement. For overhead lines this starts with wider corridors and progress to assessment of routes and alignments. For substations, we start with a long list of sites, which is refined through further assessment to identify one site. Consultation with stakeholders is essential throughout this process so that their views can be taken account of in our considerations prior to progressing to the next stage.
The culmination of this process identifies a ‘proposed option’ that will be taken forward to detailed design, environmental assessment and consent applications.
-
Consultations began at an early stage of project development, long before any decisions on power line routes or substation locations were made.
Tower locations were not shown because this information is not yet known. Early feedback is crucial, so potential route options were discussed with key stakeholders.
Our goal at this initial stage is to select routes approximately 1km wide that minimise physical or environmental obstacles and disturbances, while also being practical and cost-effective. We presented these routes to the public, statutory and non-statutory organisations to explain our current assessment and thoughts and listen to feedback.
Stakeholder feedback guides our projects from the start. All feedback is considered, and where possible and feasible, adjustments can be made, in which case we will ensure any changes are presented at future consultation events.
-
Feedback importance: SSEN Transmission values feedback from stakeholders and local communities and considers it throughout the project development process.
Whilst community feedback is not our only consideration, we wish to develop all projects sensitively and to reduce impacts on communities as much as possible. Community feedback provides an essential insight into local issues that helps to refine the design, routes, and substation locations.
What we can do: Following consideration of all feedback, we consider what opportunities there are to modify our project's design, route, and substation locations.
What we can't do: We don't decide on the overall need for the Pathway to 2030 projects; that's National Energy System Operator and Ofgem's role. Therefore, we can't consult on the core necessity of these 2030 plans.
-
In November 2020, SSE became the first company to produce a Just Transition Strategy, introducing 20 key principles to ensure fairness as we move away from carbon-heavy activities and embrace climate-friendly changes.
The Pathway to 2030 projects align with these principles, promoting job opportunities, local suppliers, and preserving cultural heritage. Early in project development, SSEN Transmission made sure to engage with communities for feedback and insight.
To read more about our principals click here
-
There will be no further consultation prior to the submission of the consent applications for the proposed new 400kV OHL’s. We have undertaken public consultations at the corridor, route and alignment stages of the project development. This includes completing two best practice consultation events as part of the pre-application process for Section 37 applications, please see Electricity Act 1989 - sections 36 and 37: applications guidance - gov.scot.
In March 2025 we concluded the alignment stage consultation for the proposed new 400kV overhead line (OHL) projects, where we presented the Proposed Alignments we will submit as part of a Section 37 applications for consent. The Proposed Alignments have been refined from the various options that we have investigated during the development of the project.
Our alignment proposals presented at these consultations were the result of extensive engagement and project design. We plan to submit our Section 37 applications to the Scottish Government’s Energy Consents Unit (ECU) in Spring 2025. Once an application for consent has been submitted, there will be an opportunity for the public to make formal representations to the ECU before it takes a decision.
For our substation proposals, most consultations concluded in May and June 2024, with applications for full planning permission, under the Town and Country Planning (Scotland) Act 1997, now submitted to the relevant local authorities for consideration. In accordance with the Town and Country Planning (Environmental Impact Assessment) (Scotland) Regulations 2017, applications were accompanied by an Environmental Impact Assessment (EIA) Reports, details of which can be viewed on the relevant project web pages.
Environmental considerations
-
Environmental Impact Assessment Reports (EIARs) for the Pathway to 2030 projects will be prepared for the chosen options, in line with the relevant legislation.
Once completed, the EIARs will be accessible online via our project website, the Scottish Government’s Energy Consents Unit applications portal, and relevant Local Authority planning portals (depending on the consent being applied for).
Hard copies will also be available to view locally and these will be advertised at the time.
-
When developing proposed project alignments, we seek to minimise impacts on woodlands and forestry where possible, however given the numerous environmental and technical constraints, some impacts are unavoidable.
Where the proposed alignment passes through woodland and forestry, an Operational Corridor is identified and trees are removed within the Operational Corridor to ensure the safe operation of the overhead line. Detailed forestry assessments are carried out as part of the Environmental Impact Assessment (EIA) reports that are submitted with Section 37 consent applications to Scottish Ministers, and these assessments are used to inform the Operational Corridor design through woodland.
The Operational Corridor width for a 400kV overhead line will typically be 45m either side of the centre line of the overhead line, but this width may vary depending on the type of woodland/forestry and local topography. In accordance with the Scottish Government’s Control of Woodland Removal Policy, we are committed to providing appropriate compensatory planting for any net loss of woodland.
-
We prioritise environmental protection in our infrastructure projects, strictly adhering to environmental policies and regulations.
We follow a mitigation hierarchy strategy of “avoid, minimise, mitigate and restore” to safeguard local, national and international designated environmentally protected areas.
As the first developer to consult upon and implement an award winning approach to deliver Biodiversity Net Gain (BNG) on all new sites, we’re committed to delivering a “greener grid”, focusing on habitat restoration and creating biodiversity growth as we invest in our network. We are committed to delivering 10% Biodiversity Net Gain on all sites gaining consent going forward. This ensures that we don’t just restore our natural habitats but actively improve them for the benefit of local communities, wildlife, flora and fauna.
During our assessments, comprehensive surveys identify potentially affected wildlife, guiding mitigation efforts. For example, bird surveys are ongoing, with winter surveys planned for 2023/24.
We also assess habitats and other species along our routes. Our consultation process to date has highlighted sensitive areas, and we continue to work with environmental experts and seek community feedback to refine our approach.
-
Scotland has protected areas that represent the very best of our landscapes, plants and animals, rocks, fossils, landforms and cultural heritage. These protected areas are also known as designated sites. The purpose of the designated site is to ensure that the features of special interest, for which the site is designated, remain in good health for all to enjoy, now and in the future.
Designated sites are usually identified by a site boundary and a definition explaining why the site has been designated. Designated sites have different levels of protection, some are protected by international and national legislation or through national and local planning policy. Some sites can have more than one designation e.g. A Site of Special Scientific Interest (SSSI) may also be designated as a Special Protection Area (SPA).
Statutory Authorities such as Nature Scot, Historic Environment Scotland (HES) and Local Authorities can identify and designate a site for its special feature(s).
Examples of designated sites are:
Dalroy and Clava Landforms SSSI - This SSSI is renowned for its “high-level shell beds”. These fossil rich marine clays occur at around 150m above present sea-level and were first recorded in the 1800’s. Clava is also noted as a particularly fine example of “flow tills”. The presence and composition of the till provides a key to understanding the location of glaciers during the last ice age as well as the direction in which they moved. SiteLink - Dalroy and Clava Landforms SSSI
Crathes Castle Garden & Designed Landscape (GDL) - Most famous for its outstanding gardens which were started in the early 17th century and were admired by Gertrude Jekyll in the 1930s. The wider 18th-century designed landscape of parkland and woodland makes an impressive setting for the A-listed castle. CRATHES CASTLE (GDL00119)
-
When planning our overhead line and substation projects, we thoroughly consider environmental, cultural, and built heritage factors in potential locations.
We make use of national archives and data sources as well as gathering data from Local Authorities and detailed site surveys to identify and assess the potential impact on archaeological sites, listed buildings, and other heritage assets.
Environmental Impact Assessment Reports (EIARs) detail these findings and recommend ways to lessen any potential adverse effects. We've received feedback about sensitive archaeological and cultural sites from a range of stakeholders, including local heritage and archaeological groups, all of which our environmental experts have considered.
-
We are committed to ensuring that all our access to land is subject to appropriate levels of biosecurity protocol in line with the relevant industry or Government biosecurity guidance, and to ensure that both practical and reasonable measures are adopted.
All of our contractors have been instructed to implement stringent biosecurity measures on taking access to properties for survey and investigation works and then for construction works, as and when our projects reach this stage, to minimise the risk of contamination and the spread of animal and plant diseases, parasites and non-native species. The guidance we provide contractors reflects a two-stage process.
- Stage 1:
- Clean footwear, vehicles, plant, tools, and temporary access materials to remove soil and debris with brush and water.
- Use facilities provided by landowners for cleaning footwear and machinery.
Stage 2:
- Clean footwear and machinery with suitable disinfectant if land is affected by disease or high risk of contamination.
- Clean between different areas within a property if requested by the landowner
Additional measures include soil sampling and testing for Potato Cyst Nematode and Clubroot where there are potato crops, transporting machinery via low-loader for thorough wash-down between properties and frequent internal team meetings to review and update biosecurity measures.
It is important that landowners take any opportunity to engage with our contractors and land managers on biosecurity concerns and inform them of any known disease on the property to allow for appropriate mitigation measures.
- Stage 1:
-
When planning routes for overhead lines and substations, we consider visual impacts and how this may affect the local scenery, visitor experience and communities.
For each project we develop, we conduct a Landscape and Visual Impact Assessment. This is one element of the Environmental Impact Assessment Reports that forms part of our application to the local authorities and Scottish Government. In this assessment, we consider visual impact from centres of population, popular spots, like walking paths and tourist sites, and where possible reduce any potential negative visual impacts.
-
When developing overhead lines and substations, we focus on having a minimal noise impact. Detailed noise assessments are conducted as part of our Environmental Impact Assessment, and include current noise levels, potential new noise as a result of our infrastructure, and mitigation measures where required, to ensure noise is within acceptable levels.
-
The impact of noise on people is heavily dependent on the nature of the noise, time of day and the noise receptor. As such, there is no single decibel level that can be applied. We engage with the relevant Local Authority’s Town and Country Planning Team to agree practical noise limits to ensure that there is no adverse impact on nearby residential properties.
Specifically, noise impacts for overhead lines are assessed having regard to external and internal noise impacts. The impact of external noise is determined by comparing the noise from the overhead line to the existing background noise levels combined with the noise sensitivity of the receptor. This is a complex assessment but dependent on context. An increase at the noise receptor of 10dB is likely to indicate a significant adverse impact and an increase of 5dB is likely to indicate an adverse impact. Internal noise resulting from external noise is calculated assuming a partially open window, that being in accordance with the guidance in BS 8233 (Guidance on sound insulation and noise reduction for buildings)
Construction noise has been assessed using BS 5228-1 (Code of practice for noise and vibration control on construction and open sites – Noise).
A detailed description of how noise impacts have been assessed is included in our submissions for consent under Section 37 of the Electricity Act 1989 to Scottish Ministers.
-
An aviation impact assessment, including engagement with key stakeholders, has determined there is no identified requirement for flashing lights on top of the towers.
In the UK, the lighting of obstacles is guided by two main documents:
- The Air Navigation Order (ANO) Article 222;
- Civil Aviation Publication (CAP) 168
CAP 168: Licensing of Aerodromes | UK Civil Aviation Authority
-
In our early project development, we consider flood risks and drainage. We aim to avoid areas prone to flooding and conduct assessments when necessary.
Our team includes a variety of water and flooding experts who help design systems to manage water flow around our sites. Before construction, we will have a plan in place to protect both surface and groundwater and reduce potential impacts.
-
The Pathway to 2030 and clean power depends upon a safe, reliable and resilient electricity transmission system that connects homes and businesses with renewable generators. The north of Scotland, with its vast renewable energy resource, plays a critical role in the energy transition. Our ambition is for our network to have the capability to meet 20% of Great Britain’s demand for clean power by 2030. This means investing to grow the network, while working with our stakeholders to ensure the transition is fair and sustainable. We recognise that the unprecedented pace and scale of network expansion will have impacts on communities, on the natural environment, and on the climate.
We are committed to leaving a positive legacy, for people, the environment, the economy, and our wider world.
Our Sustainability Strategy sets out our priorities for a transition that is fair and sustainable. Developed through an inclusive and evidence-based process, this Strategy informs our decision making and action up to and including 2030.
In 2024/25 alone, our existing network transmitted 17.1 TWh of renewable electricity, which displaced a total of 3.5 million tonnes of CO2e in one year. This is with 11GW of renewable generation capacity connected to our network. We estimate that our reinforcements out to 2030 will allow the connection of at least another 11GW, with corresponding increases to the amount of renewable electricity transmitted and associated carbon emissions displaced. In contrast, we estimate the total embodied carbon from our Pathway to 2030 construction programme to be around 2 million tonnes of CO2e. On this narrow basis, the carbon payback period for the network infrastructure would be less than a year. Read more here.
Community and landowner considerations
-
Following the publication of UK Government guidance, every transmission project with new substations or overhead line will provide a community benefit fund. Funding will consist of a strategic fund available to all communities across our network area and local funds for communities close to new infrastructure. If our planned projects go ahead, this funding is worth in excess of £100m to communities over the coming years.
Community Benefit Funds enable us to give back to the communities hosting our transmission network and to help fund projects that can leave a lasting, positive legacy in those areas.
Additionally, our projects will boost the economy, supporting local jobs and businesses. Independent studies show our Pathway to 2030 programme could contribute over £6bn to the UK's economy, support 20,000 jobs across the UK, and benefit Scotland by around £2.5bn, supporting 9,000 jobs.
-
The UK Government has proposed that people living near new transmission infrastructure across Great Britain will get money off their energy bills, as part of its Plan for Change for clean power by 2030.
Under powers in the UK Government’s proposed Planning and Infrastructure Bill, households within 500 metres of new or upgraded electricity transmission infrastructure will get electricity bill discounts of up to £2,500 over 10 years.
Details of how and when the bill discount scheme will be implemented are currently under development by the UK Government but are expected to be in place from 2026. More information can be found here.
You can find further information on the separate SSEN Transmission Community Benefit Fund here:
-
We value engaging with local communities and residents to gather feedback on our plans. While our projects can cause some uncertainty, we aim to be transparent and start these discussions early. We always welcome and encourage suggestions on improving our approach and work collaboratively with communities as our projects evolve.
-
We would like to reassure you that we develop, build and operate our infrastructure to meet all health and safety legislation, and guidance set by relevant bodies - including the UK Government, Scottish Government, the Health and Safety Executive and the industry regulator, Ofgem – including guidance associated with EMF exposure.
In respect of EMFs, we strictly follow the guidance set by the UK Government, which is informed by international guidance.
As well as setting exposure limits that protect against known, established effects of EMFs; the UK Government’s guidance includes precautionary measures to protect against possible effects below the exposure limits.
The UK Health Security Agency and Department of Health have a remit to review new research in this area and ensure that current guidelines and policies are reflective of that research.
There have been over four decades of research looking into whether EMFs associated with electricity transmission projects can cause health effects and there are no established effects below the exposure limits. When we design our overhead lines, substations and cables we do so to ensure they will not exceed those exposure limits, even when operating at 100% capacity, and we also ensure that precautionary measures are also applied to the design where required.
The guidance we follow, which remains subject to ongoing review as required, ensures that safety measures will be applied to our 400kV infrastructure protecting us all against EMF exposure, and keeping our network safe for the public.
More information is available in our EMF Leaflet.
-
We understand that there are concerns about the potential impact of our proposed developments on properties within the vicinity of SSEN Transmission’s proposed overhead line alignments and substations sites.
Throughout the development of projects SSEN Transmission has looked to mitigate impacts on residential properties as far as possible, and these impacts will be assessed as part of the Environmental Impact Assessments that accompany our applications for consent. Extensive surveys have been carried out at identified receptors, including selected residential properties so that we are able to model potential impacts on the wider area.
Concerns in relation to impacts on property are being noted by our team. However, as a regulated business, SSEN Transmission is obliged to follow a statutory legal framework under the Electricity Act 1989 and Land Compensation Act 1961. If you are entitled to compensation under the legal framework we will assess any claim on a case-by-case basis under the direction of this legal framework. If this is the case, we will recommend that you engage a professional adviser and SSEN Transmission will generally meet reasonably incurred professional fees in these circumstances. However, for the avoidance of doubt, we should advise that SSEN Transmission will not meet fees incurred in objecting to our proposed developments.
-
We aim to work cooperatively with stakeholders, including landowners, during the development of the projects.
While we might need to acquire land for substations or rights for overhead lines, our preference is to reach voluntary agreements. Using statutory powers is an absolute last resort.
If we do use them, we'll ensure fair compensation based on established industry standards.
-
A Notice of Intended Entry is a formal notice given to landowners and occupiers, based on the Electricity Act 1989.
It grants us and our contractors the right to enter land after 14 days to conduct surveys related to our project, including environmental assessments, engineering walkovers, and drone surveys.
It's essential to note that these letters are not linked to compulsory land purchase. If there are any concerns, recipients can contact us using the information provided in the letter.
-
We have statutory obligations to maintain a minimum ground clearance between conductors and other objects which are included in Regulation 17 of ESQCR 2002. Further guidance of standard clearances for the industry are set out in Energy Networks Association Technical Specification (ENA) TS 43-8.
The minimum clearance from the nearest line conductor to any object which is ordinarily accessible (including permanently mounted ladders and access platforms) or to any surface of a building is 5.3m. This includes temporary structures such as mobile and construction equipment. We provide guidance and information to third parties who intend to develop land near our electricity transmission assets, this includes overhead lines, pylons, substations, and underground cables. Find out more here.
Cost and engineering considerations
-
The required technology for the new 400kV overhead lines which form part of the Pathway to 2030 have been determined to be a new double circuit 400kV HVAC (High Voltage Alternating Current) overhead line.
The overhead line would consist of steel lattice towers with an average height of approx. 57m which would support six conductor bundles on six cross arms and an earth wire between the peaks for lightning protection. The average distance between towers is expected to be 338m. Tower height and the distance between them will vary dependent on several factors such as altitude, climatic conditions and topography.
This is similar to our Beauly—Denny line, where 80% of its 600-plus towers are below 57m, ranging from 42m to 65m in height.
-
The cost of improving the electricity network is covered by GB electricity consumers. It's to balance this cost with environmental, technical, and societal factors.
In April 2025, the Institution of Engineering and Technology published independent research undertaken to determine the difference in cost between different technology options for electricity transmission infrastructure, comparing the typical cost of overhead lines, underground and subsea cables. The study found that, typically:
- Undergroundcables cost around 4.5x more than comparable overhead lines; and
- Subsea cables cost up to 11x more than comparable overhead lines.
We conduct a Cost Benefit Analysis for our projects, but the cheapest options aren't always chosen. Factors like minimising environmental impact or ensuring technical viability also play an important part in this.
SSEN Transmission's return on investment is determined by Ofgem's regulations, no matter what the technology used.
-
In their assessment of the upgrades required to the GB Transmission Network to meet the UK Government’s 50GW of offshore wind 2030 target, National Electricity Operator assessed a number of potential solutions comprising both onshore and offshore schemes. Their Pathway to 2030 Holistic Network Design (HND), which was assessed and recommended as a single integrated GB wide network plan, concluded that a combination of both onshore and offshore schemes is required to transport the volumes of generation necessary to meet 2030 targets to key centres of demand across the country.
Overhead lines can carry roughly three times more power than subsea cables, making them more efficient and cost effective for energy bill payers.
These onshore reinforcements will also strengthen network reliability and security of supply for homes and businesses across the north of Scotland. -
Where a line exists, it doesn’t necessarily mean that it would be appropriate to build a new one next to it, there are many considerations as to why this may not be possible.
Sometimes, there is no space for new infrastructure due to existing constraints, including proximity to homes. However, in some areas, it is possible to place new lines near the old ones.
These aspects are considered in the optioneering phases of our projects for which we also seek stakeholder views.
-
The environmental, technical, and operational constraints associated with undergrounding at extra high voltages, particularly 400kV, make the option extremely challenging to deliver in many areas of Scotland.
Some of the challenges that contribute to this position:
- Technical Limitations: No underground cables for these high voltages (275kV or 400kV) currently exist in our area. Underground cables need specific ground conditions and present challenges in maintenance and power restoration, especially if faults occur.
- Environmental Impact: Undergrounding can have lasting environmental effects, for example impacts on habitats and hydrology, and the area required for laying cables needs to be clear from significant constructions or vegetation for easy access during construction and repairs.
- Terrain Concerns: The region's terrain often has slopes that are difficult to install and finding a suitable route for underground cables without challenges is extremely difficult.
- Infrastructure Needs: For underground cables longer than 1-2km, additional substation infrastructure would be needed, enlarging the project's footprint.
- Operational needs: Restoring power in the event of a cable fault can take significantly longer than for an overhead line. Faults on overhead electricity lines can typically take a few hours to a few days to repair and are generally easy to locate. Underground cable faults often require extensive works, specialist resource, tools and equipment to locate the fault, followed by significant civils work to expose the damage, replace the damaged section and then it can take up to a month to carry out the repairs. This presents significant risks to security of supply and network reliability. It also impacts on our ability to meet our licence obligations of maintaining an efficient transmission network.
- Cost: Underground cables at 400kV are estimated to be between 5 and 10 times more expensive than overhead lines, and since these costs are reflected in consumer bills, it's a factor that needs to be considered.
Even if technically feasible, undergrounding over a significant length of or the entirety of a project would be unreasonable as it would be contrary to our licence obligations to be economic and efficient in respect of additional costs to the end consumer and also have additional risk to the electricity transmission network in the event of cable failure and consequent outages.
Given these constraints and our responsibility for an economical and efficient transmission network, overhead lines are our main choice for the onshore ASTI projects. Where there is a clear evidence base to justify undergrounding, this will be carefully considered.
- Technical Limitations: No underground cables for these high voltages (275kV or 400kV) currently exist in our area. Underground cables need specific ground conditions and present challenges in maintenance and power restoration, especially if faults occur.
-
The choice between underground cables and overhead lines is based on the technology used and the power requirements:
- Technology Type: The Western Isles connection uses High Voltage Direct Current (HVDC) technology, suitable for connecting the Western Isles' power generation. This HVDC technology has low electrical losses and provides better control over the island's network conditions. It requires only two cables for a 1.8GW rating.
- Power Requirements: The Pathway to 2030 projects, including routes like Spittal-Beauly, requires a 400kV onshore overhead line to transport much more power, 5GW. This setup permits the connection of much more generation. Achieving this rating with HVDC would necessitate at least three subsea cables.
- Feasibility: Using underground cables for such high ratings isn't viable technically, economically, or environmentally due to the sheer number of cables needed.
While underground cables work for the Western Isles connection, they aren't practical for the larger Pathway to 2030 projects.
- Technology Type: The Western Isles connection uses High Voltage Direct Current (HVDC) technology, suitable for connecting the Western Isles' power generation. This HVDC technology has low electrical losses and provides better control over the island's network conditions. It requires only two cables for a 1.8GW rating.
-
While the T-Pylon has been developed for use in England and Wales, it is not currently deemed suitable for our projects in the north of Scotland for several reasons:
- Weather Impact: Our region experiences more severe weather conditions, with increased impact from wind and ice. Using T-Pylons would mean shorter spans between structures, resulting in more structures, thus increasing the visual impact, land occupation, and construction traffic.
- Material Lifespan: The composite material used for T-Pylon's diamond insulators might only last about 20 years. In contrast, the glass insulators on our lattice steel towers have a life expectancy of 40-50 years.
- Transport & Delivery: The T-Pylon's large steel sections need a large number of low-loaders for delivery, significantly affecting local traffic. Their design could also force new lines to be closer to major roads, impacting our ability to route away from properties. Lattice steel towers are more compact for transport, minimising traffic disturbance.
- Design Flexibility: T-Pylons can only turn up to 30° angles, while our lattice steel towers can turn up to 90°. This flexibility helps us avoid communities, viewpoints, and environmentally crucial sites. The limited direction change of T-Pylons would hinder our ability to minimise line impact.
- Reliability & Repair: T-Pylons support an entire circuit on a single diamond so in the unlikely event of a failure the entire circuit could be lost, whereas lattice steel pylons use a double circuit. Repairs would take significantly longer, delaying power restoration.
Given these factors, we've determined that T-Pylons aren't currently suitable for our projects, as they might result in greater community and environmental impact and increased construction traffic.
- Weather Impact: Our region experiences more severe weather conditions, with increased impact from wind and ice. Using T-Pylons would mean shorter spans between structures, resulting in more structures, thus increasing the visual impact, land occupation, and construction traffic.
-
The conductor types being utilised for the new overhead lines proposed between Spittal - Beauly, Beauly – Peterhead and Kintore – Tealing are conventional AAAC (All Aluminium Alloy Conductors). This technology is used extensively on our existing network and has a proven record of safe and reliable operation. A conductor selection exercise was carried out considering electrical performance, EMF (Electric and Magnetic Fields) and noise impacts, mechanical performance, reliability and cost. The key advantages over the other conductors considered was proven reliability, the ability to reduce conductor noise and reduce electrical losses.
-
High tension Low Sag (HTLS) conductors are particularly well suited for re-conductoring projects, where existing transmission lines are upgraded by replacing the current conductors with newer, higher capacity alternatives. These projects do not require new towers or structures, making HLTS conductors a practical option due to their reduced sag under load.
Despite these advantages, HTLS conductors also present several significant limitations. Their unique composition introduces challenges in construction, operation and maintenance. These challenges become more pronounced in areas with undulating or uneven terrain; conditions that are present along large sections of our proposed new 400kv overhead lines. Such topography places additional mechanical stress on the conductors, which HTLS types are less capable of handling compared to conventional conductors.
If these challenges are not carefully managed, they can lead to reduced asset lifespans and an increased risk of unplanned outages. In addition, addressing these issues typically extends installation timelines.
Another important consideration is that HTLS conductors tend to exhibit higher electrical losses than conventional conductors (AAACs) – particularly when operating near capacity. These losses reduce the amount of electricity delivered to end users, with the cost of this inefficiency ultimately reflected in consumer energy bills.
Given these factors, HTLS conductors were not considered appropriate for our proposed Pathway to 2030 new overhead line projects but are being utilised for one of our related re-conductoring projects.
-
Limits of Deviation (LoD) comprise an area which defines the practical limits within which movement of the Overhead Line (OHL) towers, conductors and access tracks can be sited and construction can be undertaken within the terms of the Section 37 planning consent.
A vertical and horizontal LoD is typically applied to OHL projects. The vertical LoD relates to the addition of a further section of a tower. It also applies should the foundation design change or the location of the tower move to a higher elevation. Whilst the structure height won’t change these activities can result in the tower height increasing.
The horizontal LoD is a distance either side of the OHL and access tracks. This is typically 100 – 200 metres for OHLs and 50 metres for access tracks. However, the distance applied on either side can vary and be project specific.
LoDs are required to provide the flexibility needed during construction to adapt to unforeseen circumstances. This helps ensure that the consented project design can still be implemented even if unexpected engineering or environmental challenges arise.
An example of where a LoD may be utilised is where poor ground conditions are identified that may make the planned location of infrastructure impractical or less suitable. In such cases, the infrastructure position, initially shown in the plans, can be adjusted to a new location within the LoD, allowing construction to proceed. Any movement of infrastructure within the LoD must be agreed by the project team and assessed against the Environmental Impact Assessment Report submitted with the Section 37 application, before the change in location can proceed.
-
All project documents, which include maps of the suggested routes for the overhead lines can be found on our project webpages. Contact details of your local Community Liaison Manager are also available.
-
The 3D models used at our consultation events are created by combining several datasets with the project's proposed infrastructure integrated into them. The base model consists of a 5m resolution Digital Terrain Model (DTM), overlaid with high quality 25cm aerial imagery and 1:25,000 scale Ordnance Survey mapping. It also includes detailed road layouts. On top of this, our consultants incorporate building shapes and tree locations using specialised national data.
Terrain
The model uses OS Terrain 5 data from Ordnance Survey to shape the group surface in the model.This dataset is created from high-resolution scans and simplified to a 5-metre resolution for use in 3D modelling. You can find more information about the dataset here.
Aerial Imagery
The model uses 25cm resolution aerial photos, also from Ordnance Survey. These images are collected on a rolling three-year cycle and matched to Terrain 5 data for accuracy. You can find more information about the dataset here.
TreesTree locations come from the National Tree Map, supplied by Bluesky. It shows vegetation over 3 metres tall, classifying it as either conifer or broadleaf, and represents them using typical tree shapes. You can find more information about the dataset here.
Buildings
The model uses Level of Detail 2 building data from Bluesky. This includes accurately shaped pitched and flat roof shapes, based on high-resolution stereo aerial imagery. You can find more information about the dataset here.
All of this information is georeferenced using the British National Grid Projection. This ensures that every part of the model lines up correctly , making it accurate when integrating proposed infrastructure.
The 3D models are based on geospatial data at the time of modeling. While the data is regularly reviewed and updated, the model may not reflect recent changes, such as newly constructed buildings, recently removed structures or vegetation. changes (e.g. felled trees). This model is intended to give a general visual impression and may not capture every detail of the current environment.
Western Isles Project Contacts
Kevin Morrison | Community Liaison Manager
Jamie Cowie | Land Manager
Mainland HVDC Converter Station Project Contacts
Sally Cooper | Community Liaison Manager
Chris Mangnall | Consultant Land Manager
Telephone: 07803 498931
Address: 10 Henderson Road, Inverness, IV1 1SN
Recite me
To make use of this function please click on the 3 'A's' button at the bottom left of the website.
Latest Links
-
Report on Consultation
Our Reports on Consultation across our three new overhead line projects and associated substation and convertor station developments have now been published. These reports provide a summary of the extensive feedback received during consultation, how this has been considered and confirmation of which routes and substations are now being taken forward to the next stage of development.
Our Reports on Consultation are now available to download from the Project Documentation tab.
Summary Reports on Consultation are also available for each of the three schemes and can be downloaded below:
- Summary Report on Consultation Spittal to Beauly
- Summary Report on Consultation Beauly to Peterhead
- Summary Report on Consultation Kintore to Tealing
A stakeholder webinar available for all to join will be held in the coming weeks to share the changes informed by the feedback. More information about the forthcoming webinar will be shared on our events page shortly.
In further recognition of community feedback, we will seek to rationalise cumulative infrastructure impacts through the removal and undergrounding of existing transmission lines, where technically practical and appropriate, and subject to all necessary planning consents and landowner agreements.
Work to identify and assess potential sections of existing overhead line where their removal will reduce cumulative impacts is ongoing, with an update expected as part of the next round of public consultation on overhead line alignments and more detailed substation designs in early 2024.
We would once again like to thank all stakeholders who took the time to engage with our early consultation process. We will continue to engage with stakeholders ahead of consulting further with local communities and stakeholders in the new year, as we look to refine our proposals.
-
Report on Consultation
Over the course of this year, we have undertaken extensive consultation on plans to upgrade the electricity transmission network across the north of Scotland and have received a considerable amount of feedback from a wide range of stakeholders regarding our proposals.
We recently advised in our next steps for 2030 network developments update that following assessment of consultation feedback and additional options analysis, we would publish our Report on Consultations (RoCs). These reports provide a summary of the feedback received and how it has been considered, which options we will take forward to the next stage of the development process and any changes to options initially consulted on.
It is our intention to publish the RoCs during the week commencing 27 November. All stakeholders signed up for updates on the project will receive a link to the report and we will also issue Summary Reports to help ensure accessibility.
These Report on Consultations mark the completion of the first round of non-statutory consultation, where we sought feedback on the corridor, route, and substation locations. We will be consulting further with local communities and stakeholders in the new year, as we look to refine the projects, therefore we welcome an open channel of communication and would like to reassure all stakeholders that there will be further opportunities to engage on this project.
Our Reports on Consultation and Summary Reports on Consultation are now available to download from the Project Documentation tab. -
SSEN Transmission sets out next steps for Pathway to 2030 network developments
We have announced our next steps for our Pathway to 2030 programme of projects. We would like to thank everyone who has engaged with our teams and kindly taken the time to respond to our consultations.
Full details of the announcement can be found here:
Next steps for Pathway to 2030