Overview
Alignment Consultation Events
We recently held a series of 15 public events across the project route from 20 May until 20 June 2024, with over 900 members of the public registered as attending one of our events. We would like to extend a thank you to those who took the time to attend our events, meet with the team, and share their views on our proposals.
During the consultation we shared our potential alignment for the overhead line, with alternative alignment options in some locations, presented through maps and visualisations.
Accessing information online
For those who were unable to attend the consultation events, we have created an interactive consultation portal where you can view and download content from the consultation events and access photosphere visualisations of the overhead line. All documents relating to the consultation are also available to download from the 'documents' tab at the top of this page.
Our Environmental Consultants, WSP, have created a story map where you can find out more information on the project and access our maps interactively.
Visualisations Slideshow
Our consultants 3D Webtech, have created a slideshow containing some visualisations from their 3D model available at the consultation events. To access this slideshow, please see the video below.
About the Project
In order to support the continued growth in onshore and offshore renewables across the north of Scotland, supporting the country's drive towards Net Zero, investment in network infrastructure is needed to connect this renewable power and transport it from source to areas of demand across the country.
Extensive studies have confirmed the need for a new 400kV connection between Beauly and Peterhead, connecting into substation sites at Blackhillock and New Deer. The project includes the following elements:
- A new 400kV connection between Beauly and Blackhillock
- A new 400kV connection between Blackhillock and New Deer
- A new 400kV connection between New Deer and Peterhead
- New 400kV substations and associated infrastructure at Beauly, Blackhillock, New Deer and Peterhead
- Removal of the existing 132kV overhead line from Beauly to Knocknagael following establishment of the new 400kV connection
Find Out More About New Beauly Area 400kV Substation
Find Out More About New Blackhillock 400kV Substation
Find Out More About New Deer 2 400kV Substation
Find Out More About Peterhead 2030 Developments
3D Model
We have a 3D model which allows users to view the overhead line from view points across the project route.
Pathway to 2030
The Pathway to 2030, published by National Grid ESO, the electricity system operator for Great Britain, sets the blueprint for the electricity transmission network infrastructure required to enable the forecasted growth in renewable electricity across Great Britain.
The projects identified within the Pathway to 2030 are critical to delivering the UK and Scottish Government’s offshore wind targets. To deliver these targets, we are investing over £10bn to upgrade the network infrastructure across the north of Scotland as the region plays a leading role in the clean energy transition.
As part of this investment, there is a requirement for a new 400kV connection between Beauly and Peterhead.
Explore Pathway to 2030 Projects
This video outlines how the project contributes to our role in delivering Net Zero.
How we’re embracing artificial intelligence (AI)
We intend to use AI to assist our experienced teams in the analysis of your feedback, so we can categorise key points raised more quickly. You can learn more about how we’re utilising AI on this dedicated web page.
Project Updates
Featured updates
Featured updates for this project
Project updates
Documents
Turriff & District CC Public Meeting Presentation
Alignment Consultation Materials - May & June 2024
Alignment Consultation Document and Figures
Pathway to 2030 Projects - Additional Information
Refined Routeing Stage - Update Event
Routeing Stage Report on Consultation
Routeing Stage Consultation Event Materials
Corridor Stage Consultation Materials
FAQs
Who we are
About the Pathway to 2030 projects
Our approach to routeing and public consultation
Environmental considerations
Communities and landowner considerations
Cost and engineering considerations
Recite me
To make use of this function please click on the 3 'A's' button at the bottom left of the website.
Latest Links
-
Report on Consultation
Our Reports on Consultation across our three new overhead line projects and associated substation and convertor station developments have now been published. These reports provide a summary of the extensive feedback received during consultation, how this has been considered and confirmation of which routes and substations are now being taken forward to the next stage of development.
Our Reports on Consultation are now available to download from the Project Documentation tab.
Summary Reports on Consultation are also available for each of the three schemes and can be downloaded below:
- Summary Report on Consultation Spittal to Beauly
- Summary Report on Consultation Beauly to Peterhead
- Summary Report on Consultation Kintore to Tealing
A stakeholder webinar available for all to join will be held in the coming weeks to share the changes informed by the feedback. More information about the forthcoming webinar will be shared on our events page shortly.
In further recognition of community feedback, we will seek to rationalise cumulative infrastructure impacts through the removal and undergrounding of existing transmission lines, where technically practical and appropriate, and subject to all necessary planning consents and landowner agreements.
Work to identify and assess potential sections of existing overhead line where their removal will reduce cumulative impacts is ongoing, with an update expected as part of the next round of public consultation on overhead line alignments and more detailed substation designs in early 2024.
We would once again like to thank all stakeholders who took the time to engage with our early consultation process. We will continue to engage with stakeholders ahead of consulting further with local communities and stakeholders in the new year, as we look to refine our proposals.
-
Report on Consultation
Over the course of this year, we have undertaken extensive consultation on plans to upgrade the electricity transmission network across the north of Scotland and have received a considerable amount of feedback from a wide range of stakeholders regarding our proposals.
We recently advised in our next steps for 2030 network developments update that following assessment of consultation feedback and additional options analysis, we would publish our Report on Consultations (RoCs). These reports provide a summary of the feedback received and how it has been considered, which options we will take forward to the next stage of the development process and any changes to options initially consulted on.
It is our intention to publish the RoCs during the week commencing 27 November. All stakeholders signed up for updates on the project will receive a link to the report and we will also issue Summary Reports to help ensure accessibility.
These Report on Consultations mark the completion of the first round of non-statutory consultation, where we sought feedback on the corridor, route, and substation locations. We will be consulting further with local communities and stakeholders in the new year, as we look to refine the projects, therefore we welcome an open channel of communication and would like to reassure all stakeholders that there will be further opportunities to engage on this project.
Our Reports on Consultation and Summary Reports on Consultation are now available to download from the Project Documentation tab. -
SSEN Transmission sets out next steps for Pathway to 2030 network developments
We have announced our next steps for our Pathway to 2030 programme of projects. We would like to thank everyone who has engaged with our teams and kindly taken the time to respond to our consultations.
Full details of the announcement can be found here:
Next steps for Pathway to 2030