Overview
Planning Application
Following the second pre application consultation feedback events that were hosted in June at several locations within Angus and Perth and Kinross we can confirm that we have now submitted our S37 consent application to the Scottish Ministers at the Energy Consents Unit (ECU).
The Alyth – Tealing OHL upgrade is part of a wider upgrade to the transmission network in the north of Scotland, helping deliver high voltage, clean renewable power for connection to homes and businesses across the UK – helping meet national net zero and energy security ambitions.
Under Section 37 of the Electricity Act 1989 we have applied to Scottish Ministers for consent to upgrade approximately 14km of the existing 275kV OHL between Alyth substation and Tower 685 north west of Tealing substation, to enable operation at 400kV.
Should you wish to view our application in full and submit formal comment to the Scottish Ministers it is available to be viewed via the ECU’s application portal, using reference ECU00005167. Any representations in respect of the application may be submitted by email to the Scottish Government via representations@gov.scot; or by post to the Scottish Government, Energy Consents Unit, 4th Floor, 5 Atlantic Quay, 150 Broomielaw, Glasgow, G2 8LU, identifying the proposal and specifying the grounds for representation.
All the documentation submitted as part of the application can also be viewed and downloaded via the documents section of this webpage.
We would like to thank those who provided feedback as part of our pre-application consultation events, which have been key in helping us shape our proposals and we now look forward to working with the Scottish Government and other key stakeholders as part of the consenting process.
About the Project
In order to support the continued growth in onshore and offshore renewables across the north of Scotland, supporting the country's drive towards Net Zero, investment in network infrastructure is needed to connect this renewable power and transport it from source to areas of demand across the country.
To support the increased capacity from the proposed Kintore – Tealing 400kV Connection, the export routes to areas of demand must be upgraded to 400kV. This means the existing Alyth – Tealing and Tealing – Westfield overhead lines, which currently operate at 275kV, need to be upgraded to operate at 400kV.
This is part of the East Coast 400kV projects, a scheme consisting of several onshore reinforcement projects on the east coast of Scotland.
Find Out More About Kintore to Tealing 400kV Connection
This video outlines how the project contributes to our role in delivering Net Zero.
Pathway to 2030
The Pathway to 2030, published by National Grid ESO, the electricity system operator for Great Britain, sets the blueprint for the electricity transmission network infrastructure required to enable the forecasted growth in renewable electricity across Great Britain.
The projects identified within the Pathway to 2030 are critical to delivering the UK and Scottish Government’s offshore wind targets. To deliver these targets, we are investing over £20bn to upgrade the network infrastructure across the north of Scotland as the region plays a leading role in the clean energy transition.
As part of this investment, there is a requirement for the Alyth - Tealing overhead line 400kV upgrade project.
Stakeholder Engagement
Public consultations took place in May 2023 to inform the community on progress to date with the East Coast 400kV Phase 2 Projects. We sought feedback from local communities and all interested parties on all the projects that make up the scheme.
Access the 2023 Virtual Exhibition
In this video, Senior Project Manager Calum Grant describes the approach we are taking to develop our proposals and the opportunities that are available for stakeholders to feed into the design process.
The East Coast 400kV Projects
The East Coast 400kV projects are a scheme consisting of several onshore reinforcement projects on the east coast of Scotland, comprising new and upgrade of existing infrastructure. The majority of the infrastructure projects are within our operational area in the north of Scotland.
To provide the full 400kV capability that the scheme intends to deliver, there are several projects that contribute to the full scheme:
- An extension to Kintore 400kV substation (currently under construction)
-
A new 400kV substation within the vicinity of the existing Fetteresso substation
-
A new 400kV substation within the vicinity of the existing Tealing substation
-
A new 400kV connection between Kintore and Tealing
-
An upgrade to the existing Alyth - Tealing 275kV overhead line
-
An upgrade to the existing Tealing - Westfield 275kV overhead line (to the Scottish Power Transmission operational border)
-
Connection of the upgraded Alyth - Tealing and Tealing - Westfield overhead lines into the proposed Tealing substation
Find out more about Kintore 400kV substation
Find out more about Hurlie 400kV substation
Find out more about Emmock 400kV substation
How we’re embracing artificial intelligence (AI)
We intend to use AI to assist our experienced teams in the analysis of your feedback, so we can categorise key points raised more quickly. You can learn more about how we’re utilising AI on this dedicated web page.
Project Updates
Featured updates
Featured updates for this project
Planning Application
Project updates
Documents
Planning Application - Covering Letter
Planning Application - EIA Report Volume 1: Non Technical Summary
Planning Application - EIA Report Volume 2: Main Report
Planning Application - EIA Report Volume 3: Figures and Visualisations
Planning Application - EIA Report Volume 4: Appendices
Planning Application - Pre Application Consultation (PAC) Report
Planning Application - Planning Statement
Planning Application - Socio Economic Assessment
Planning Application - EMF Study
Planning Application - Public Notice
June 2024 public consultation documents
-
June 2024 public consultation event booklet
- Type:
- Date:
- 20 May 2024
- Size:
- 4.3 MB
This document provides information to our stakeholders about the project and was provided during our consultation in June 2024.
-
June 2024 public consultation event times
- Type:
- Date:
- 20 May 2024
- Size:
- 121 KB
This document provides information to our stakeholders about our consultation events in June 2024.
March 2024 public consultation documents
-
Re-conductoring location map
- Type:
- Date:
- 19 February 2024
- Size:
- 676.6 KB
These maps provide information to our stakeholders about the location of the project.
-
March 2024 re-conductoring public consultation booklet
- Type:
- Date:
- 19 February 2024
- Size:
- 2.7 MB
This document provides information to our stakeholders about the project and was provided during our consultation in March 2024.
-
March 2024 public consultation times
- Type:
- Date:
- 19 February 2024
- Size:
- 141.3 KB
This document provides information to our stakeholders about our consultation events in March 2024.
Pathway to 2030 Projects - Additional Information
May 2023 public consultation documents
-
East Coast 400kV Phase 2 Initial consultation feedback response June 2023
- Type:
- Date:
- 13 June 2023
- Size:
- 314.8 KB
-
May 2023 public consultation information booklet
- Type:
- Date:
- 19 April 2023
- Size:
- 19.4 MB
-
Route sections A-F constraint maps
- Type:
- Date:
- 19 April 2023
- Size:
- 24.4 MB
-
Corridor options
- Type:
- Date:
- 18 April 2023
- Size:
- 4.4 MB
-
Fiddes substation site selection
- Type:
- Date:
- 18 April 2023
- Size:
- 4.2 MB
-
Preferred corridor
- Type:
- Date:
- 18 April 2023
- Size:
- 5.6 MB
-
Preferred route
- Type:
- Date:
- 18 April 2023
- Size:
- 5.3 MB
-
Route options
- Type:
- Date:
- 18 April 2023
- Size:
- 5.4 MB
-
Route options section A
- Type:
- Date:
- 18 April 2023
- Size:
- 4.4 MB
-
Route options section B
- Type:
- Date:
- 18 April 2023
- Size:
- 5.8 MB
-
Route options section C
- Type:
- Date:
- 18 April 2023
- Size:
- 6 MB
-
Route options section D
- Type:
- Date:
- 18 April 2023
- Size:
- 4.5 MB
-
Route options section E
- Type:
- Date:
- 18 April 2023
- Size:
- 6.1 MB
-
Route options section F
- Type:
- Date:
- 18 April 2023
- Size:
- 6.3 MB
-
Tealing substation site selection
- Type:
- Date:
- 18 April 2023
- Size:
- 4.4 MB
Project documents
-
Delivering a positive environmental legacy
- Type:
- Date:
- 28 April 2023
- Size:
- 5 MB
-
2023 Public Consultation Times
- Type:
- Date:
- 06 April 2023
- Size:
- 147.2 KB
-
Grantors Charter
- Type:
- Date:
- 15 March 2023
- Size:
- 176.2 KB
-
East Coast 400kV Phase 2 Information Booklet
- Type:
- Date:
- 13 December 2022
- Size:
- 4.4 MB
FAQs
Who we are
About the Pathway to 2030 projects
Our approach to routeing and public consultation
Environmental considerations
Communities and landowner considerations
Cost and engineering considerations
Recite me
To make use of this function please click on the 3 'A's' button at the bottom left of the website.
Latest Links
-
Report on Consultation
Our Reports on Consultation across our three new overhead line projects and associated substation and convertor station developments have now been published. These reports provide a summary of the extensive feedback received during consultation, how this has been considered and confirmation of which routes and substations are now being taken forward to the next stage of development.
Our Reports on Consultation are now available to download from the Project Documentation tab.
Summary Reports on Consultation are also available for each of the three schemes and can be downloaded below:
- Summary Report on Consultation Spittal to Beauly
- Summary Report on Consultation Beauly to Peterhead
- Summary Report on Consultation Kintore to Tealing
A stakeholder webinar available for all to join will be held in the coming weeks to share the changes informed by the feedback. More information about the forthcoming webinar will be shared on our events page shortly.
In further recognition of community feedback, we will seek to rationalise cumulative infrastructure impacts through the removal and undergrounding of existing transmission lines, where technically practical and appropriate, and subject to all necessary planning consents and landowner agreements.
Work to identify and assess potential sections of existing overhead line where their removal will reduce cumulative impacts is ongoing, with an update expected as part of the next round of public consultation on overhead line alignments and more detailed substation designs in early 2024.
We would once again like to thank all stakeholders who took the time to engage with our early consultation process. We will continue to engage with stakeholders ahead of consulting further with local communities and stakeholders in the new year, as we look to refine our proposals.
-
Report on Consultation
Over the course of this year, we have undertaken extensive consultation on plans to upgrade the electricity transmission network across the north of Scotland and have received a considerable amount of feedback from a wide range of stakeholders regarding our proposals.
We recently advised in our next steps for 2030 network developments update that following assessment of consultation feedback and additional options analysis, we would publish our Report on Consultations (RoCs). These reports provide a summary of the feedback received and how it has been considered, which options we will take forward to the next stage of the development process and any changes to options initially consulted on.
It is our intention to publish the RoCs during the week commencing 27 November. All stakeholders signed up for updates on the project will receive a link to the report and we will also issue Summary Reports to help ensure accessibility.
These Report on Consultations mark the completion of the first round of non-statutory consultation, where we sought feedback on the corridor, route, and substation locations. We will be consulting further with local communities and stakeholders in the new year, as we look to refine the projects, therefore we welcome an open channel of communication and would like to reassure all stakeholders that there will be further opportunities to engage on this project.
Our Reports on Consultation and Summary Reports on Consultation are now available to download from the Project Documentation tab. -
SSEN Transmission sets out next steps for Pathway to 2030 network developments
We have announced our next steps for our Pathway to 2030 programme of projects. We would like to thank everyone who has engaged with our teams and kindly taken the time to respond to our consultations.
Full details of the announcement can be found here:
Next steps for Pathway to 2030