Overview
Opportunity to ask outstanding questions about the proposed Fanellan project
The final proposed alignment statutory consultation events for the overhead lines connecting into the proposed Fanellan site start next week and events will be taking place at various locations over the coming weeks. Project team members from the Spittal to Beauly and Beauly to Peterhead overhead line project teams will be in Kiltarlty and Beauly next week to discuss their proposals.
In addition some of the project team members from the Fanellan project will be in attendance at these two events to provide you the opportunity to ask any outstanding questions you may have about the proposed Fanellan project.
Wednesday 19th February @ Kiltarllity Village Hall from 3pm-7pm
Thursday 20th February @ Phipps Hall, Beauly from 2.30pm-6.30pm
Increased Construction Traffic
Our principal contractor SeimensBam have informed us they need to increase the size of their working compound while the ground investigation works continue.
From now onwards until the end of February there will be an increase in construction traffic in the area while additional site cabins, plant and aggregate are brought to site to carry out this work.
Where required larger plant will be escorted and will travel from the A833 through Kiltarlity village, turn right before Culburnie and travel onwards, turning left at the Fanellan junction up to the site compound beside the bottling plant.
Plant is expected to demobilise around the 27th and 28th February.
To minimise any local impacts the contractor will carry out these deliveries after 9.30am and avoiding times between 3pm-4.15pm and between 12-1pm on Fridays.
We anticipate minimal impacts from these traffic movements, though if impacts do occur we do apologise.
-
Fanellan Red Line Boundary: Ground investigation works are progressing as planned.
These works are required to determine ground conditions for further design and program refinement and will be taking place over the coming months within different sections of the proposed red line boundary area.
They are being undertaken on private land, off public roads and will be carried out in 2 phases by our principal contractor SiemansBam. Works will involve 3 equipment rigs and site staff doing bore holes and trial pits at any one time. There are also some outstanding ecological surveys, which will be concluded in the same area during these works.
-
Overhead Line Projects: In the coming months there will also be some local ground investigation works due to be carried out by the Beauly – Peterhead Overhead Line project team.
Dates and details are still in the process of being confirmed and we will update you once a programme is agreed.We don't anticipate any local disturbance to arise as a result of these works, however residents in closest proximity will be informed in advance of works commencing and we will communicate any updates should changes should they occur.
About the Project
In order to support the continued growth in onshore and offshore renewables across the north of Scotland, supporting the country's drive towards Net Zero, investment in network infrastructure is needed to connect this renewable power and transport it from source to areas of demand across the country.
Extensive studies have confirmed the need to reinforce the onshore transmission infrastructure between Spittal to Beauly and Beauly to Peterhead, the need for a subsea cable between Spittal and Peterhead, and a subsea/onshore cable between Beauly and the Western Isles.
To enable these reinforcements, a new 400kV substation is required within a 10km radius of Beauly and will connect to:
- A new Beauly Area HVDC Converter Station
- The existing Beauly/Wester Balblair 400kV Substation
- The existing Beauly - Denny 400kV Overhead Line
- A new 400kV connection between Spittal and Beauly
- A new 400kV connection between Beauly and Peterhead
Find Out More About Spittal - Loch Buidhe - Beauly 400kV Connection
Find Out More About Beauly - Blackhillock - New Deer - Peterhead 400kV Connection
This video outlines how the project contributes to our role in delivering Net Zero.
Pathway to 2030
The Pathway to 2030, published by National Energy System Operator NESO, the electricity system operator for Great Britain, sets the blueprint for the electricity transmission network infrastructure required to enable the forecasted growth in renewable electricity across Great Britain.
The projects identified within the Pathway to 2030 are critical to delivering the UK and Scottish Government’s offshore wind targets. To deliver these targets, we are investing over £10bn to upgrade the network infrastructure across the north of Scotland as the region plays a leading role in the clean energy transition.
As part of this investment, there is a requirement for a new 400kV substation in the Beauly area.
Stakeholder Engagement
The New Fanellan 400kV substation and Converter Station project is currently in the development stages and is subject to extensive consultation with stakeholders.
In this video, Rebecca Gay and Martin Godwin, Project Manager and Community Liaison Manager for the Spittal to Beauly Overhead Line Project, describe the approach we are taking in developing our proposals and the opportunities that are available for stakeholders to feed into the design process.
How we’re embracing artificial intelligence (AI)
We intend to use AI to assist our experienced teams in the analysis of your feedback, so we can categorise key points raised more quickly. You can learn more about how we’re utilising AI on this dedicated web page.
Project Updates
Featured updates
Featured updates for this project

Proposed Fanellan project: Notification of increased construction traffic

Overhead Line Local Engagement Events - Feb/March '25
Project updates
Documents
Pre-Application Consultation Documents 2 (PAC2) - June 2024
-
Connections into Fanellan and Permanent Requirements Layout Plan.pdf
- Type:
- Date:
- 10 June 2024
- Size:
- 2.7 MB
These maps provide information to our stakeholders about the connections into the proposed Fanellan site and the Fanellan permanent requirements layout plan for the site.
-
Western Isles handout.pdf
- Type:
- Date:
- 06 June 2024
- Size:
- 6.7 MB
This material provides information to our stakeholders about the Western Isles Connection into Fanellan Converter Station.
-
Fanellan temporary requirements layout.pdf
- Type:
- Date:
- 06 June 2024
- Size:
- 950.8 KB
This map provides information to our stakeholders about the Fanellan temporary requirements layout plan for the site.
-
Fanellan Consultation Poster.pdf
- Type:
- Date:
- 06 June 2024
- Size:
- 105 KB
This material provides information to our stakeholders about the project and consultation events in June 2024.
-
Fanellan Consultation Banners.pdf
- Type:
- Date:
- 06 June 2024
- Size:
- 7 MB
This material provides information to our stakeholders about the project.
-
Fanellan Consultation Booklet.pdf
- Type:
- Date:
- 06 June 2024
- Size:
- 25.5 MB
This Pre-Application Consultation Booklet (and associated appendices/maps) explains the project need and summarises the process which has been followed to arrive at the optimal site. It forms part of the consultation exercise which provides all interested parties with the opportunity to provide feedback.
Pre-Application Consultation Documents (PAC)
-
Feedback Event Poster - Jun 2024
- Type:
- Date:
- 03 June 2024
- Size:
- 105 KB
This material provides information to our stakeholders about the project and consultation events in June 2024.
-
Western Isles Connection Handout.pdf
- Type:
- Date:
- 18 March 2024
- Size:
- 6.7 MB
This material provides information to our stakeholders about the Western Isles Connection into Fanellan Converter Station.
-
Fanellan red line boundary with permanent site requirements, February 2024.pdf
- Type:
- Date:
- 14 March 2024
- Size:
- 19.4 MB
This map provides information to our stakeholders about the Proposal of Application Notice (PAN) red line boundary for the site.
-
Beauly Area Pathway to 2030 projects overview.pdf
- Type:
- Date:
- 14 March 2024
- Size:
- 2.2 MB
This map provides information to our stakeholders about connections into the proposed Fanellan site.
-
Proposal of application boundary map showing indicative permanent requirments.pdf
- Type:
- Date:
- 14 March 2024
- Size:
- 3.2 MB
This map provides information to our stakeholders about the Proposal of Application Notice (PAN) boundary map showing indicative permanent requirements.
-
Fanellan poster.pdf
- Type:
- Date:
- 13 March 2024
- Size:
- 69.1 KB
This material provides information to our stakeholders about the project and consultation events in June 2024.
-
Overview of environmental features and designations in the wider area.pdf
- Type:
- Date:
- 13 March 2024
- Size:
- 5.3 MB
This map provides information to our stakeholders with an overview of environmental features and designations in the wider area.
-
Fanellan Consultation Banners.pdf
- Type:
- Date:
- 13 March 2024
- Size:
- 9.2 MB
This material provides information to our stakeholders about the project.
-
Fanellan Consultation Booklet.pdf
- Type:
- Date:
- 13 March 2024
- Size:
- 16.5 MB
This Pre-Application Consultation Booklet (and associated appendices/maps) explains the project need and summarises the process which has been followed to arrive at the optimal site. It forms part of the consultation exercise which provides all interested parties with the opportunity to provide feedback.
Pathway to 2030 Projects - Additional Information
Project Documents
-
Nov 23 CLG Project updates and Meeting Notes.pdf
- Type:
- Date:
- 14 December 2023
- Size:
- 2.7 MB
-
Nov 23 CLG RoC preview Summary and Meeting Notes.pdf
- Type:
- Date:
- 14 December 2023
- Size:
- 2.7 MB
-
Beauly CLG - Beauly Substation Workshop - Nov 23.pdf
- Type:
- Date:
- 05 December 2023
- Size:
- 2.2 MB
-
Aug CLG meeting notes Final.pdf
- Type:
- Date:
- 23 November 2023
- Size:
- 8.7 MB
-
Beauly 400kV Substation Hub_Site Selection_Consultation Document Sep 2023.pdf
- Type:
- Date:
- 05 October 2023
- Size:
- 5 MB
-
Final Beauly CLG Meeting Notes June 2023.pdf
- Type:
- Date:
- 07 September 2023
- Size:
- 3.3 MB
-
Beauly CLG Meeting Notes April 2023.pdf
- Type:
- Date:
- 27 July 2023
- Size:
- 2.1 MB
-
Beauly CLG Meeting Notes Feb 2023.pdf
- Type:
- Date:
- 27 July 2023
- Size:
- 1.3 MB
-
Beauly CLG Meeting Notes November 2022.pdf
- Type:
- Date:
- 27 July 2023
- Size:
- 852.8 KB
-
Beauly CLG Meeting Notes August 2022.pdf
- Type:
- Date:
- 27 July 2023
- Size:
- 1.1 MB
-
Consultation Report - Spittal - Loch Buidhe - Beauly - July 23.pdf
- Type:
- Date:
- 13 July 2023
- Size:
- 1.3 MB
-
Spittal - Beauly Consultation response May 2023.pdf
- Type:
- Date:
- 17 May 2023
- Size:
- 166.2 KB
-
Spittal-Loch Buidhe-Beauly initial consultation feedback response 28.03.23.pdf
- Type:
- Date:
- 28 March 2023
- Size:
- 199.9 KB
-
Beauly Main Site Options Map with Legend.pdf
- Type:
- Date:
- 01 March 2023
- Size:
- 70.5 MB
-
Consultation Booklet new Beauly Area site Selection and Spittal - Beauly OHL route.pdf
- Type:
- Date:
- 17 February 2023
- Size:
- 67.3 MB
-
Public Consultation Poster - Feb/March 2023
- Type:
- Date:
- 06 February 2023
- Size:
- 101 KB
Reports on Consultation
-
RoC - New Beauly Area 400kV Substation - Figure 2 - Proposed Site.pdf
- Type:
- Date:
- 01 December 2023
- Size:
- 1.6 MB
-
Report on Consultation - New Beauly Area 400kV Substation and HVDC Converter Station.pdf
- Type:
- Date:
- 01 December 2023
- Size:
- 2.3 MB
-
Summary ROC - Spittal to Beauly.pdf
- Type:
- Date:
- 01 December 2023
- Size:
- 4.8 MB
-
Summary ROC - Beauly to Peterhead.pdf
- Type:
- Date:
- 01 December 2023
- Size:
- 2.8 MB
-
RoC - Beauly - Peterhead OHL - Figure 4.10 Proposed Route to be taken to Alignment.pdf
- Type:
- Date:
- 01 December 2023
- Size:
- 5.8 MB
-
RoC - Beauly - Peterhead OHL - Figure 1.1 - Route Options Shared at Consultations.pdf
- Type:
- Date:
- 01 December 2023
- Size:
- 10.6 MB
-
RoC - Beauly - Peterhead OHL - Preferred Route with Amendments.pdf
- Type:
- Date:
- 01 December 2023
- Size:
- 14.1 MB
-
RoC - Beauly to Spittal OHL - Figure 1 - Route Options Presented at Consultation.pdf
- Type:
- Date:
- 01 December 2023
- Size:
- 6.7 MB
-
RoC - Beauly to Spittal OHL - Figure 2 - Proposed Route options to take forward to alignment phase.pdf
- Type:
- Date:
- 01 December 2023
- Size:
- 6.1 MB
-
Report on Consultation - Spittal to Loch Buidhe to Beauly Overhead Line.pdf
- Type:
- Date:
- 01 December 2023
- Size:
- 3.2 MB
-
Report on Consultation - Beauly to Blackhillock to New Deer to Peterhead 400kV OHL.pdf
- Type:
- Date:
- 01 December 2023
- Size:
- 3.9 MB
FAQs
Who we are
About the Pathway to 2030 projects
Our approach to routeing and public consultation
Environmental considerations
Communities and landowner considerations
Cost and engineering considerations
Recite me
To make use of this function please click on the 3 'A's' button at the bottom left of the website.

Latest Links
-
Report on Consultation
Our Reports on Consultation across our three new overhead line projects and associated substation and convertor station developments have now been published. These reports provide a summary of the extensive feedback received during consultation, how this has been considered and confirmation of which routes and substations are now being taken forward to the next stage of development.
Our Reports on Consultation are now available to download from the Project Documentation tab.
Summary Reports on Consultation are also available for each of the three schemes and can be downloaded below:
- Summary Report on Consultation Spittal to Beauly
- Summary Report on Consultation Beauly to Peterhead
- Summary Report on Consultation Kintore to Tealing
A stakeholder webinar available for all to join will be held in the coming weeks to share the changes informed by the feedback. More information about the forthcoming webinar will be shared on our events page shortly.
In further recognition of community feedback, we will seek to rationalise cumulative infrastructure impacts through the removal and undergrounding of existing transmission lines, where technically practical and appropriate, and subject to all necessary planning consents and landowner agreements.
Work to identify and assess potential sections of existing overhead line where their removal will reduce cumulative impacts is ongoing, with an update expected as part of the next round of public consultation on overhead line alignments and more detailed substation designs in early 2024.
We would once again like to thank all stakeholders who took the time to engage with our early consultation process. We will continue to engage with stakeholders ahead of consulting further with local communities and stakeholders in the new year, as we look to refine our proposals.
-
Report on Consultation
Over the course of this year, we have undertaken extensive consultation on plans to upgrade the electricity transmission network across the north of Scotland and have received a considerable amount of feedback from a wide range of stakeholders regarding our proposals.
We recently advised in our next steps for 2030 network developments update that following assessment of consultation feedback and additional options analysis, we would publish our Report on Consultations (RoCs). These reports provide a summary of the feedback received and how it has been considered, which options we will take forward to the next stage of the development process and any changes to options initially consulted on.
It is our intention to publish the RoCs during the week commencing 27 November. All stakeholders signed up for updates on the project will receive a link to the report and we will also issue Summary Reports to help ensure accessibility.
These Report on Consultations mark the completion of the first round of non-statutory consultation, where we sought feedback on the corridor, route, and substation locations. We will be consulting further with local communities and stakeholders in the new year, as we look to refine the projects, therefore we welcome an open channel of communication and would like to reassure all stakeholders that there will be further opportunities to engage on this project.
Our Reports on Consultation and Summary Reports on Consultation are now available to download from the Project Documentation tab. -
SSEN Transmission sets out next steps for Pathway to 2030 network developments
We have announced our next steps for our Pathway to 2030 programme of projects. We would like to thank everyone who has engaged with our teams and kindly taken the time to respond to our consultations.
Full details of the announcement can be found here:
Next steps for Pathway to 2030